PROJECT CONSTRUCTION UPDATES: OCTOBER 2022

PROJECT CONSTRUCTION UPDATES: OCTOBER 2022

SONIA SOTOMAYOR MIDDLE SCHOOL AT ADELPHI

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Installation of exterior metal wall panels and spray fireproofing in all other areas completed.
  • Paving at the vehicular parking area 80% complete.
  • MEP rough-in in sector 2B and drywall close-in on level 1 of sector 1B completed.
  • Foundations for the main entrance canopy completed.
  • Retaining wall at the southeast parking area and underground electrical duct bank completed.

Work In Progress:

  • Site underground storm water piping and underground water piping in progress.
  • MEP rough-in sectors 2K and 2G in progress.
  • Installation of interior door frames and wall close-ins throughout sector 1 in progress.
  • Electrical in wall rough-in on level 2 of sector 1A in progress.
  • Installation of the north site retaining wall, main entrance canopy, and elevator in progress.
  • Painting of classrooms and all CMU walls in progress.

30-Day Look Ahead:

  • Interior stud wall framing and MEP ceiling rough-ins in sectors 2K and 2G to continue.
  • Installation of the site underground utilities is ongoing.
  • Installation of interior door frames, canopy steel structure, and TPO roofing to continue.
  • MEP in wall rough-ins on level 2 of sector 1B is ongoing.
  • Paining classrooms and all CMU walls in sectors 1A and 1B is ongoing.

COLIN L. POWELL K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • All secondary steel girt framing completed.
  • Exterior metal wall panels at east and north areas completed.
  • TPO roofing at the 3-story and 4-story towers completed.
  • Interior CMU walls in the choir, dance, and music rooms completed.
  • Spray fireproofing on level 1 of the 3-story tower completed.
  • Overhead MEP rough-in on levels 2 and 3 of the 4-story tower completed.
  • In-wall inspections on level 1 of the north classroom wing completed.
  • Asphalt paving at the west parking area completed. 

Work in Progress:

  • Spray fireproofing, overhead MEP rough-in, and exterior brick at the 3-story tower in progress.
  • Installation of exterior brick and TPO roofing at the west entrance in progress.
  • Installation of exterior metal wall panels at the 4-story tower in progress.
  • Interior painting in the kitchen in progress.
  • Hanging and finishing of drywall in the north classroom wing in progress.
  • Landscaping at the west parking area in progress.

30-Day Look Ahead:

  • Spray fireproofing on level 2 of the 3-story tower to begin.
  • Road widening at Swan Creek Road is ongoing.
  • Installation of exterior metal wall panels is ongoing.
  • Interior stud wall framing on level 1 of the 3-story tower – Level 1 is ongoing.
  • Installation of ACT ceiling grid in the kitchen to begin.
  • Installation of the 4-story tower elevator is ongoing.

DREW-FREEMAN MIDDLE SCHOOL


Project Executive: 
Christian Broyles 
Past Month’s Accomplishments:

  • Spray fireproofing and TPO roofing in sectors 1 and 2 completed.
  • Interior wall blocking in sector 1B completed.
  • Interior stud wall framing on level 2 of sectors 1A and 1B completed.
  • Ductwork in sector 2 commons completed.
  • Window framing in sector 2K and exterior metal wall panels in sector 2G completed.

Work in Progress:

  • Exterior windows and interior stud wall framing in sector 2K in progress.
  • Hanging drywall in sector 1A in progress.
  • Ductwork in sectors 2G and 2K in progress. 

30-Day Look Ahead:

  • Wall close-Ins in sector 1B to begin.
  • One-side drywall in sectors 1A and 1B is ongoing.
  • Rough-in fire protection in sectors 2G and 2K is ongoing.
  • Concrete sidewalks and parking lot concrete curb and gutters to be completed. 
  • Asphalt at parking lots to begin.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Drywall one-siding interior walls on levels 2 and 3 of sector 1A completed.
  • Fire sprinkler installation and electrical in wall rough-in in sector 1B completed.
  • Telecom cabling installation on level 3 of sectors 1A and 1B completed.
  • Electrical power distribution rough-in on levels 1 and 2 of sector 1A completed.
  • Interior stud wall framing and one-siding drywall on level 4 of sector 1B completed.
  • Interior door frame installation on levels 1 to 3 of sector 1A completed.
  • Grading and undercutting and underground site utilities under parking lots completed.
  • Underground gas utilities at north end of site completed.
  • Interior paint at back of house spaces completed.
  • RTU roof curbs completed.

Work in Progress:

  • Trim out exterior metal panels and gutters and downspouts at sectors 2G and 2K in progress. 
  • Drywall close in, finishing interior walls, and interior door frame installation at sector 1A in progress.
  • Fire sprinkler installation, electrical in wall rough-in, and electrical power distribution rough-ins at sector 1B in progress.
  • Telecom cabling installation in sectors 1A and1B in progress.
  • Concrete curb and gutter at lower parking lot in progress.
  • Elevator installation in progress.

30-Day Look Ahead:

  • MEP, sprinkler, and telecom overhead rough-ins, testing, and insulation are ongoing.
  • Base asphalt paving at the lower lot to begin.
  • Rough-ins at the main mechanical and electrical rooms are ongoing.
  • Water testing of exterior window units to be completed.
  • One-siding walls at the kitchen and performance rooms to begin.
  • Prime paint and first coat at classrooms and corridors in sector 1A to begin.
  • ACT ceiling grid installation at the sector 1A tower to begin.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • In-wall MEP Rough-in sectors 1A and 2K completed.
  • Drywall close-in at sector 1B completed.
  • One-side drywall installation in sector 1A completed.
  • Underground chilled water line pipe and interior gas line installation and inspection completed.

Work in Progress:

  • Drywall finishing and electrical room buildout and branch wire pull in sector 1A and 1B in progress.
  • Overhead duct work and piping insulation in sector 2G in progress.
  • One-side drywall installation in sector 2K in progress.
  • Main electrical feeders, mechanical room rough-in and final connection to electrical equipment in progress.
  • Interior knock down door frame installation throughout the building in progress.
  • Installation of underground main water and gas lines to building in progress.
  • Wall close-in inspection in sector 1A in progress.
  • Electrical in-wall rough-ins at sector 2B in progress..

30-Day Look Ahead:

  • Wall close-ins un sector 1A to be completed.
  • Electrical in-wall rough-ins at sectors 2A and 2B are ongoing.
  • Underground storm pipe MH 24 – MH 25 – MH 27 to begin.
  • Temporary heat installation to begin.
  • WSSC Water and Gas inspections to be completed
  • Bus parking lot parking lot curbs, gutters and asphalt base to begin.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Interior MEP overhead rough-ins on level 2 of sector 1B completed.
  • Interior stud wall framing on level 2 sector 1A and 2K completed.
  • Hanging and finishing drywall and prime paint walls on level 1 of sector 1B completed.
  • Hanging of drywall on level 1 and installation of door frames on level 2 of sector 1A completed.

Work in Progress:

  • Interior MEP overhead and in-wall rough-ins in sectors 1A and 1B in progress.
  • Soil nail retaining wall at back of school site in progress.
  • Installation of stairs 1 and 3 and elevator in the sector 1 media center in progress.
  • Underground site utilities in west parking lot in progress.
  • Caulking of exterior windows and installation of exterior storefront doors in progress.
  • Main mechanical room rough-ins in sector 2K in progress.

30-Day Look Ahead:

  • Underground site utilities throughout the project site is ongoing.
  • Hanging of one-sided drywall and first coat interior paint in sector 1B to begin.
  • Soil nail retaining wall installation to continue. 
  • Drywall finishing and prime paint on level 1 of sector 1A to begin.
  • MEP rough-ins in sector 2K mechanical and electrical rooms to be completed.
  • Installation of ACT ceiling grid on level 1 of sector 1B to begin.

*Please note: Construction timeframes shown above are subject to change.