01 Nov PROJECT CONSTRUCTION UPDATES: OCTOBER 2022
SONIA SOTOMAYOR MIDDLE SCHOOL AT ADELPHI

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of exterior metal wall panels and spray fireproofing in all other areas completed.
- Paving at the vehicular parking area 80% complete.
- MEP rough-in in sector 2B and drywall close-in on level 1 of sector 1B completed.
- Foundations for the main entrance canopy completed.
- Retaining wall at the southeast parking area and underground electrical duct bank completed.
Work In Progress:
- Site underground storm water piping and underground water piping in progress.
- MEP rough-in sectors 2K and 2G in progress.
- Installation of interior door frames and wall close-ins throughout sector 1 in progress.
- Electrical in wall rough-in on level 2 of sector 1A in progress.
- Installation of the north site retaining wall, main entrance canopy, and elevator in progress.
- Painting of classrooms and all CMU walls in progress.
30-Day Look Ahead:
- Interior stud wall framing and MEP ceiling rough-ins in sectors 2K and 2G to continue.
- Installation of the site underground utilities is ongoing.
- Installation of interior door frames, canopy steel structure, and TPO roofing to continue.
- MEP in wall rough-ins on level 2 of sector 1B is ongoing.
- Paining classrooms and all CMU walls in sectors 1A and 1B is ongoing.
COLIN L. POWELL K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- All secondary steel girt framing completed.
- Exterior metal wall panels at east and north areas completed.
- TPO roofing at the 3-story and 4-story towers completed.
- Interior CMU walls in the choir, dance, and music rooms completed.
- Spray fireproofing on level 1 of the 3-story tower completed.
- Overhead MEP rough-in on levels 2 and 3 of the 4-story tower completed.
- In-wall inspections on level 1 of the north classroom wing completed.
- Asphalt paving at the west parking area completed.
Work in Progress:
- Spray fireproofing, overhead MEP rough-in, and exterior brick at the 3-story tower in progress.
- Installation of exterior brick and TPO roofing at the west entrance in progress.
- Installation of exterior metal wall panels at the 4-story tower in progress.
- Interior painting in the kitchen in progress.
- Hanging and finishing of drywall in the north classroom wing in progress.
- Landscaping at the west parking area in progress.
30-Day Look Ahead:
- Spray fireproofing on level 2 of the 3-story tower to begin.
- Road widening at Swan Creek Road is ongoing.
- Installation of exterior metal wall panels is ongoing.
- Interior stud wall framing on level 1 of the 3-story tower – Level 1 is ongoing.
- Installation of ACT ceiling grid in the kitchen to begin.
- Installation of the 4-story tower elevator is ongoing.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Spray fireproofing and TPO roofing in sectors 1 and 2 completed.
- Interior wall blocking in sector 1B completed.
- Interior stud wall framing on level 2 of sectors 1A and 1B completed.
- Ductwork in sector 2 commons completed.
- Window framing in sector 2K and exterior metal wall panels in sector 2G completed.
Work in Progress:
- Exterior windows and interior stud wall framing in sector 2K in progress.
- Hanging drywall in sector 1A in progress.
- Ductwork in sectors 2G and 2K in progress.
30-Day Look Ahead:
- Wall close-Ins in sector 1B to begin.
- One-side drywall in sectors 1A and 1B is ongoing.
- Rough-in fire protection in sectors 2G and 2K is ongoing.
- Concrete sidewalks and parking lot concrete curb and gutters to be completed.
- Asphalt at parking lots to begin.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Drywall one-siding interior walls on levels 2 and 3 of sector 1A completed.
- Fire sprinkler installation and electrical in wall rough-in in sector 1B completed.
- Telecom cabling installation on level 3 of sectors 1A and 1B completed.
- Electrical power distribution rough-in on levels 1 and 2 of sector 1A completed.
- Interior stud wall framing and one-siding drywall on level 4 of sector 1B completed.
- Interior door frame installation on levels 1 to 3 of sector 1A completed.
- Grading and undercutting and underground site utilities under parking lots completed.
- Underground gas utilities at north end of site completed.
- Interior paint at back of house spaces completed.
- RTU roof curbs completed.
Work in Progress:
- Trim out exterior metal panels and gutters and downspouts at sectors 2G and 2K in progress.
- Drywall close in, finishing interior walls, and interior door frame installation at sector 1A in progress.
- Fire sprinkler installation, electrical in wall rough-in, and electrical power distribution rough-ins at sector 1B in progress.
- Telecom cabling installation in sectors 1A and1B in progress.
- Concrete curb and gutter at lower parking lot in progress.
- Elevator installation in progress.
30-Day Look Ahead:
- MEP, sprinkler, and telecom overhead rough-ins, testing, and insulation are ongoing.
- Base asphalt paving at the lower lot to begin.
- Rough-ins at the main mechanical and electrical rooms are ongoing.
- Water testing of exterior window units to be completed.
- One-siding walls at the kitchen and performance rooms to begin.
- Prime paint and first coat at classrooms and corridors in sector 1A to begin.
- ACT ceiling grid installation at the sector 1A tower to begin.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- In-wall MEP Rough-in sectors 1A and 2K completed.
- Drywall close-in at sector 1B completed.
- One-side drywall installation in sector 1A completed.
- Underground chilled water line pipe and interior gas line installation and inspection completed.
Work in Progress:
- Drywall finishing and electrical room buildout and branch wire pull in sector 1A and 1B in progress.
- Overhead duct work and piping insulation in sector 2G in progress.
- One-side drywall installation in sector 2K in progress.
- Main electrical feeders, mechanical room rough-in and final connection to electrical equipment in progress.
- Interior knock down door frame installation throughout the building in progress.
- Installation of underground main water and gas lines to building in progress.
- Wall close-in inspection in sector 1A in progress.
- Electrical in-wall rough-ins at sector 2B in progress..
30-Day Look Ahead:
- Wall close-ins un sector 1A to be completed.
- Electrical in-wall rough-ins at sectors 2A and 2B are ongoing.
- Underground storm pipe MH 24 – MH 25 – MH 27 to begin.
- Temporary heat installation to begin.
- WSSC Water and Gas inspections to be completed
- Bus parking lot parking lot curbs, gutters and asphalt base to begin.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Interior MEP overhead rough-ins on level 2 of sector 1B completed.
- Interior stud wall framing on level 2 sector 1A and 2K completed.
- Hanging and finishing drywall and prime paint walls on level 1 of sector 1B completed.
- Hanging of drywall on level 1 and installation of door frames on level 2 of sector 1A completed.
Work in Progress:
- Interior MEP overhead and in-wall rough-ins in sectors 1A and 1B in progress.
- Soil nail retaining wall at back of school site in progress.
- Installation of stairs 1 and 3 and elevator in the sector 1 media center in progress.
- Underground site utilities in west parking lot in progress.
- Caulking of exterior windows and installation of exterior storefront doors in progress.
- Main mechanical room rough-ins in sector 2K in progress.
30-Day Look Ahead:
- Underground site utilities throughout the project site is ongoing.
- Hanging of one-sided drywall and first coat interior paint in sector 1B to begin.
- Soil nail retaining wall installation to continue.
- Drywall finishing and prime paint on level 1 of sector 1A to begin.
- MEP rough-ins in sector 2K mechanical and electrical rooms to be completed.
- Installation of ACT ceiling grid on level 1 of sector 1B to begin.
*Please note: Construction timeframes shown above are subject to change.