News

ADELPHI MIDDLE SCHOOL Project Executive: Christian Broyles Past Month’s Accomplishments: MEPF hangers installation and interior wall layout at building sectors 2A and 2B completed.Installation and pouring of concrete stair...

ADELPHI AREA MIDDLE SCHOOL Project Executive: Christian Broyles Past Month’s Accomplishments: MEPF hangers and interior wall layout and fire proofing in building sector 1B completed.Installation of roof...

ADELPHI AREA MIDDLE SCHOOL Project Executive: Christian Broyles Past Month’s Accomplishments: Building perimeter exterior knee wall framing and MEPF hangers at building sectors 1A and 1B completed.Interior CMU block...

ADELPHI AREA MIDDLE SCHOOL Project Executive: Christian Broyles Past Month’s Accomplishments: Building perimeter knee wall framing and AVB at sector 2K completed.MEPF hangers and interior wall layout sector...

ADELPHI AREA MIDDLE SCHOOL Project Executive: Christian BroylesPast Month’s Accomplishments: All underslab plumbing and electrical completed.All concrete slabs on grade completed.Erection of steel in the Kitchen...

ADELPHI AREA MIDDLE SCHOOL Project Executive: Christian Broyles Past Month’s Accomplishments: All underslab plumbing and electrical completed.All concrete slabs on grade completed.Erection of steel in the Kitchen...