01 May Project Construction Updates: April 2022
ADELPHI AREA MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Building perimeter knee wall framing and AVB at sector 2K completed.
- MEPF hangers and interior wall layout sector 1A completed.
- Structural steel erection in sectors1A and 1B completed.
- Exterior metal panel deliveries completed.
- Elevated concrete deck pours at sector 1A completed.
- Install roof panels at sectors 2K and 2G completed.
- Metal decking and MEPF elevated concrete decks rough in sector 1B in progress.
- Interior CMU block walls in sectors 2G and 2K in progress.
- Forming and pouring of concrete stage ramp in progress.
- Building foundation wall waterproofing and backfill in progress.
- Building perimeter exterior brick knee wall sectors 2K and 2G in progress.
30-Day Look Ahead:
- Building perimeter knee wall framing and AVB at sectors 1A, 1B, and 2G is ongoing.
- Roof panel install at sectors 1A and 1B is ongoing.
- MEPF hangers and interior wall layout Sector 1B to continue.
- Exterior wall metal panel deliveries are ongoing.
- Elevated concrete deck pours at sector 1B to begin.
- Site storm water utilities install to begin.
- Interior CMU block elevator shaft walls to begin.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Erection of classroom steel in building sector 1B completed.
- Installation of metal decking in building sector 1A completed.
- Installation of concrete slabs in building sector 2K completed.
- Primary steel erection in building sector 2G completed.
- Installation of building perimeter knee wall at sector 1A in progress.
- Pouring of elevated concrete decks at sector 1A in progress.
- Installation of metal decking in building sector 1B in progress.
- Installation of secondary steel in building sector 2G in progress.
30-Day Look Ahead:
- Pouring of elevated concrete decks at sector 1A to continue.
- Installation of perimeter knee wall and secondary steel in building sectors 1A and 1B is ongoing.
- Steel erection at building sector 2K to continue.
- Installation of roof panels at sector 2G to continue.
- Rough in overhead MEPF in sector 1A is ongoing.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Pouring of elevated concrete deck in sector 1A (3rd and 4th Floors) completed.
- Primary steel erection at sectors 2G and 2K completed.
- Interior CMU block elevator shaft walls completed.
- Grading of turf field area completed.
- Secondary steel install at sector 1A in progress.
- Primary steel erection in sector 1B in progress.
- Building perimeter knee wall framing and sheathing at sector 1A in progress.
- Building foundation wall waterproofing and backfill in progress.
30-Day Look Ahead:
- Exterior metal panel deliveries to begin.
- Metal panel roof installation at sectors 2G and 2K is ongoing.
- Exterior metal wall panel installation to begin.
- MEPF hanger installation at sector 1A to continue.
- Interior wall framing and one-siding with drywall at sector 1A is ongoing.
- Installation of storm water utilities at the SW corner to begin.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of caissons at the south side of the site completed.
- Primary and secondary steel in sector 2G completed.
- Secondary steel wall girts and purlins at all building sectors completed.
- Roof decking and all elevated concrete deck pours completed.
- Roof panels in Sector 2K competed.
- Building perimeter knee wall installation in sectors 2k and 1B completed.
- Installation of MEP hangers in sector 2K and first floor of sector 1B completed.
- Entrance canopy steel erection in progress.
- Installation of interior CMU block walls in sector 2K and elevator shaft in progress.
- Installation of roof panels in sector 1B and spraying of fireproofing on first floor in progress.
- MEP hanger installation in sector 1A first floor in progress.
- Roof panels in sector 1B and move to sector 1A roof panel installation in progress.
30-Day Look Ahead:
- Interior wall layout and framing in sector 1B first floor is ongoing.
- Interior installation of ceiling hat channel and lath system in sector 2K is ongoing.
- Exterior waterproofing/AVB on sheathing/exterior brick at sector 2K to continue.
- Installation of wall panels in sector 2K to continue.
- Installation of the exterior sanitary sewer system to be completed.
- Installation of data/electrical duct banks is ongoing.
SOUTHERN AREA K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Slab on grade at east area and main gym completed.
- Removal of surcharge dirt at the SW end of the building pad completed.
- Mobilization of steel contractor and inspection of crane completed.
- Monitoring settlement of fill dirt and surcharge dirt on the building pad in progress.
- Under slab on grade plumbing and electrical at the 4-story tower in progress.
- Concrete building foundations at west side of 4-story tower in progress.
- Grading site at greenfield areas in progress.
- Delivery of primary and secondary structural steel in progress.
30-Day Look Ahead:
- Steel erection at east area to begin.
- Steel erection at north center area to begin.
- Slab on grade at north center area to be completed.
- Pouring of concrete slab on grade at 4-story tower to begin.
- Installation of metal roof decking at east area to begin.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Steel erection and detailing of steel in sector 1B completed.
- Sector 2K underground MEP and slab on grade concrete pour completed.
- Concrete building foundations at sector 2G completed.
- Steel erection in sector 1A in progress.
- Underground MEP at sector 2G in progress.
- Prepping for elevated concrete deck pour at sector 1B in progress.
30-Day Look Ahead:
- Steel erection at sector 2K to begin.
- Metal deck and detailing at sector 1A to begin.
- Pouring of elevated concrete deck at sector 1B to begin.
- Pouring of slab on grade at sector 2G to begin.
- Secondary steel install at sector 1B to begin.
*Please note: Construction timeframes shown above are subject to change.