Project Construction Updates: April 2022

Project Construction Updates: April 2022

ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:

  • Building perimeter knee wall framing and AVB at sector 2K completed.
  • MEPF hangers and interior wall layout sector 1A completed.
  • Structural steel erection in sectors1A and 1B completed.
  • Exterior metal panel deliveries completed.
  • Elevated concrete deck pours at sector 1A completed.
  • Install roof panels at sectors 2K and 2G completed.
  • Metal decking and MEPF elevated concrete decks rough in sector 1B in progress.
  • Interior CMU block walls in sectors 2G and 2K in progress.
  • Forming and pouring of concrete stage ramp in progress.
  • Building foundation wall waterproofing and backfill in progress.
  • Building perimeter exterior brick knee wall sectors 2K and 2G in progress.

30-Day Look Ahead:

  • Building perimeter knee wall framing and AVB at sectors 1A, 1B, and 2G is ongoing.
  • Roof panel install at sectors 1A and 1B is ongoing.
  • MEPF hangers and interior wall layout Sector 1B to continue.
  • Exterior wall metal panel deliveries are ongoing.
  • Elevated concrete deck pours at sector 1B to begin.
  • Site storm water utilities install to begin.
  • Interior CMU block elevator shaft walls to begin.

DREW-FREEMAN MIDDLE SCHOOL

Project Executive: Christian Broyles 
Past Month’s Accomplishments:

  • Erection of classroom steel in building sector 1B completed.
  • Installation of metal decking in building sector 1A completed.
  • Installation of concrete slabs in building sector 2K completed.
  • Primary steel erection in building sector 2G completed.
  • Installation of building perimeter knee wall at sector 1A in progress.
  • Pouring of elevated concrete decks at sector 1A in progress.
  • Installation of metal decking in building sector 1B in progress.
  • Installation of secondary steel in building sector 2G in progress.

30-Day Look Ahead:

  • Pouring of elevated concrete decks at sector 1A to continue.
  • Installation of perimeter knee wall and secondary steel in building sectors 1A and 1B is ongoing.
  • Steel erection at building sector 2K to continue.
  • Installation of roof panels at sector 2G to continue.
  • Rough in overhead MEPF in sector 1A is ongoing.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Pouring of elevated concrete deck in sector 1A (3rd and 4th Floors) completed.
  • Primary steel erection at sectors 2G and 2K completed.
  • Interior CMU block elevator shaft walls completed.
  • Grading of turf field area completed.
  • Secondary steel install at sector 1A in progress.
  • Primary steel erection in sector 1B in progress.
  • Building perimeter knee wall framing and sheathing at sector 1A in progress.
  • Building foundation wall waterproofing and backfill in progress.

30-Day Look Ahead:

  • Exterior metal panel deliveries to begin.
  • Metal panel roof installation at sectors 2G and 2K is ongoing.
  • Exterior metal wall panel installation to begin.
  • MEPF hanger installation at sector 1A to continue.
  • Interior wall framing and one-siding with drywall at sector 1A is ongoing.
  • Installation of storm water utilities at the SW corner to begin.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Installation of caissons at the south side of the site completed.
  • Primary and secondary steel in sector 2G completed.
  • Secondary steel wall girts and purlins at all building sectors completed.
  • Roof decking and all elevated concrete deck pours completed.
  • Roof panels in Sector 2K competed.
  • Building perimeter knee wall installation in sectors 2k and 1B completed.
  • Installation of MEP hangers in sector 2K and first floor of sector 1B completed.
  • Entrance canopy steel erection in progress.
  • Installation of interior CMU block walls in sector 2K and elevator shaft in progress.
  • Installation of roof panels in sector 1B and spraying of fireproofing on first floor in progress.
  • MEP hanger installation in sector 1A first floor in progress.
  • Roof panels in sector 1B and move to sector 1A roof panel installation in progress.

30-Day Look Ahead:

  • Interior wall layout and framing in sector 1B first floor is ongoing.
  • Interior installation of ceiling hat channel and lath system in sector 2K is ongoing.
  • Exterior waterproofing/AVB on sheathing/exterior brick at sector 2K to continue.
  • Installation of wall panels in sector 2K to continue.
  • Installation of the exterior sanitary sewer system to be completed.
  • Installation of data/electrical duct banks is ongoing.

SOUTHERN AREA K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Slab on grade at east area and main gym completed.
  • Removal of surcharge dirt at the SW end of the building pad completed.
  • Mobilization of steel contractor and inspection of crane completed.
  • Monitoring settlement of fill dirt and surcharge dirt on the building pad in progress.
  • Under slab on grade plumbing and electrical at the 4-story tower in progress.
  • Concrete building foundations at west side of 4-story tower in progress.
  • Grading site at greenfield areas in progress.
  • Delivery of primary and secondary structural steel in progress.

30-Day Look Ahead:

  • Steel erection at east area to begin.
  • Steel erection at north center area to begin.
  • Slab on grade at north center area to be completed.
  • Pouring of concrete slab on grade at 4-story tower to begin.
  • Installation of metal roof decking at east area to begin.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Steel erection and detailing of steel in sector 1B completed.
  • Sector 2K underground MEP and slab on grade concrete pour completed.
  • Concrete building foundations at sector 2G completed.
  • Steel erection in sector 1A in progress.
  • Underground MEP at sector 2G in progress.
  • Prepping for elevated concrete deck pour at sector 1B in progress.

30-Day Look Ahead:

  • Steel erection at sector 2K to begin.
  • Metal deck and detailing at sector 1A to begin.
  • Pouring of elevated concrete deck at sector 1B to begin.
  • Pouring of slab on grade at sector 2G to begin.
  • Secondary steel install at sector 1B to begin.

*Please note: Construction timeframes shown above are subject to change.