01 Sep PROJECT CONSTRUCTION UPDATES: August 2022
ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- MEPF hangers installation and interior stud wall layout on level 2 of building sector 1A completed.
- Installation and pouring of concrete stair tread infills at stairs 2 and 3 completed.
- Spray fireproofing on level 2 of building sector 2B completed.
- Installation of exterior metal wall panels and MEP above ceiling rough-in in building sector 1B completed.
- Underground sanitary piping installation at the parking lot area completed.
- Installation of ceiling metal lath in building sector 2K completed.
- Installation of the grease interceptor completed.
- Electrical in wall rough-in, building foundation wall waterproofing, and backfill in building sector 1B in progress.
- MEPF hangers installation and interior wall layout on level 2 of building sector 1B in progress.
- Spray fireproofing ceiling lath in building sector 2K and on level 2 of building sector 1B in progress.
- MEPF rough-in in the west commons, gym, and on level 2 of building sector 1B in progress.
- Installation of TPO roofing at the connector in progress.
- Installation of exterior windows at building sector 1B and the gym in progress.
- Installation of interior door frames in building sector 1A in progress.
- Installation of block retaining walls and site underground storm piping in progress.
30-Day Look Ahead:
- Interior stud wall framing and MEP ceiling rough-in on level 2 of building sector 1B is ongoing.
- Installation of exterior wall panels on level 2 of building sectors 1A and 1B is ongoing.
- Installation of the site underground utilities to continue.
- Detailing of TPO roofing to continue.
- Installation of exterior windows and interior door frames is ongoing.
- MEP in-wall rough-in in building sectors 1A and 1B to continue.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of exterior brick in building sector 1B completed.
- Installation of exterior wall panels and window framing in building sectors 1A and 1B completed.
- Installation of underground grease interceptor near building sector 2K completed.
- Installation of exterior windows and wall blocking in building sectors 1A and 1B in progress.
- Spray fireproofing of ceiling lath system in building sector 2K in progress.
- Installation of drywall top out in building sector 1B in progress.
- One-sided drywall installations in building sector 1A in progress.
- Installation of Stair 2 in building sector 1 in progress.
30-Day Look Ahead:
- One-sided drywall installations in sectors 1A and 1B are ongoing.
- Spray fireproofing of ceiling lath system on level 2 of building sector 1A is ongoing.
- Exterior window installations in building sector 1A and level 2 of building sector 1B are ongoing.
- Installation of stairs 1 and 3 is ongoing.
- Wall blocking installations in building sector 1A and level 2 of building sector 1B are ongoing.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Exterior metal panel and interior CMU block wall bracing installation at building sector 2G completed.
- Primary duct bank installation at north side of site completed.
- Entrance canopy framing and blocking completed
- Window installation and caulking at building sector 1A completed.
- In-wall rough-in on level 1 of building sector 1A completed.
- Drywall framing and top out in the kitchen of building sector 2K completed.
- Spray fireproofing on level 4 and stair 1 installation at the tower of building sector 1B completed.
- TPO roofing installation at connector roofs completed.
- One-siding drywall, sprinkler installation, electrical in wall rough-in, interior stud wall framing, and electrical power distribution on various level in building sector 1A in progress.
- Installation of exterior metal wall panels at building sector 1B in progress.
- Telecom cabling installation in building sectors 1A and 1B in progress.
- Sanitary tie-in at north side of site in progress.
- Grading of lower parking lot in progress.
30-Day Look Ahead:
- MEP, sprinkler, and telecom overhead rough-in testing and insulation is ongoing.
- Installation of exterior metal panels to be completed.
- Exterior window installation at building sectors 1B and 2G to begin.
- Grading of bus loop and lower lot to begin.
- Gas tie-in at north end of site to begin.
- Wall close-ins and interior door frame installation at level 1 of building sector 1A to begin.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Spray fireproofing, setting of RTU curbs, canopy outriggers, and installation of primary electrical duct bank and secondary duct bank completed.
- Interior stud wall framing in building sector 2A completed.
- Overhead ductwork in building sector 2B completed.
- Mechanical room equipment delivery to site completed.
- Electrical rough-in in building sector 1B completed.
- In-wall HVAC controls rough-in in building sector 1 completed.
- Stair 2 installation completed.
- Storm line installation from MH 15 to MH 16 completed.
- Installation of exterior wall panels at location of canopy outriggers in progress.
- Overhead duct work at building sector 2A in progress.
- Electrical room rough-in on building sector 1A in progress.
- Installation of exterior windows at the north elevation in progress.
- Chiller piping from pad to building in progress.
- Sanitary line connection from kitchen to grease interceptor to sanitary in progress.
- Building gutters and trim at IMP-Roof in progress.
- Stair 1 installation and completion of all interior stud wall framing in progress.
- Ductwork in the center section building sector 1 in progress.
- Sprinkler piping in building sectors 1A and 2B in progress.
30-Day Look Ahead:
- Wall close-in inspections and hanging of drywall in building sector 1 are ongoing.
- Overhead MEP rough-in on level 2 of building sector 2 is ongoing.
- In-wall electrical rough-ins in building sectors 1A and 2B are ongoing.
- Door frame delivery is expected.
- Chiller, transformer, and generator pad installation is ongoing.
- Installation of storm lines MH 24, MH 25, and MH 27 to begin.
- Stair 3 installation to begin.
- IMP wall panels and storefront installation to be completed.
COLIN L. POWELL K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Concrete slab on deck and spray fireproofing on various levels of the 4-story tower completed.
- Steel erection, metal decking, and detailing of the 3-story tower and west entrance completed.
- Overhead MEP rough-in in building sectors 1 and 2 completed.
- Interior wall framing in the kitchen completed.
- Concrete slab on metal deck at the 3-story tower in progress.
- Overhead MEP rough-in, secondary steel installation, and spray fireproofing on various levels of the 4-story tower in progress.
- Installation of insulated metal wall panels in building sector 1 in progress.
- Interior CMU block wall construction at the aux gym and music spaces in progress.
- Interior wall framing in the Cafeteria in progress.
- Curb and gutter of the west parking lot in progress.
- Preparation of the playfields for autumn planting season in progress.
30-Day Look Ahead:
- Interior stud wall framing in building sector 2 to begin.
- Concrete slab on metal deck at the 3-story tower is ongoing.
- Installation of insulated metal wall panels is ongoing.
- Spray fireproofing and overhead MEP rough-in in the 4-Story Tower is ongoing.
- Curb and gutter construction for parking lots and access road areas is ongoing.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Interior MEP overhead rough-in in building sector 1A completed.
- Spray fireproofing and installation of ceiling metal lath building sector 2K completed.
- Installation of exterior metal wall panels and CMU support steel at building sector 2G completed.
- Interior stud wall framing and spray fireproofing on level 2 of building sector 1B completed.
- Ceiling metal lath installation on level 2 of building sector 2A completed.
- Installation of stair 2 completed.
- Pouring of concrete stage and installation of water meter vault completed.
- Interior MEP overhead rough-in on level 2 of building sector 1B in progress.
- Installation of interior CMU block walls at building Sector 2G in progress.
- Installation of TPO roofing and windows in building sector 1 in progress.
- Interior stud wall framing in building sector 2K in progress.
- One-side drywall installation on level 1 of building sector 1B in progress.
- Installation of soil nail retaining wall in progress.
30-Day Look Ahead:
- Spray fireproofing, interior stud wall framing, and overhead MEP rough-in on level 2 of building sector 1A to begin.
- Installation of underground site utilities throughout the project site is ongoing.
- Hanging of one side drywall on level 1 of building sector 1A to begin.
- Installation of windows in building sector 2 to begin.
- Installation of door frames in building sector 1 to begin.
- Installation of soil nail retaining wall to continue.
*Please note: Construction timeframes shown above are subject to change.