PROJECT CONSTRUCTION UPDATES: DECEMBER 2022

PROJECT CONSTRUCTION UPDATES: DECEMBER 2022

SONIA SOTOMAYOR MIDDLE SCHOOL AT ADELPHI


Top Row: Classroom – drywall, paint, and ceiling grid installed (interior); Gym – drywall installation (interior)
Bottom Row: Electrical room (interior); HDPE Drainage pipe installation (exterior east side view)


Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • MEP rough-in in the gym completed.
  • Drywall close-in on level 2 of sector 1A completed.
  • Installation of the transformer completed and primary and secondary wires pulled.
  • ACT ceiling grid on level 1 of sector 1B completed.
  • Installation of part 1 of the east storm detention system completed.
  • Installation and backfill of the north retaining wall completed.

Work In Progress:

  • Installation of the remainder of the east underground storm detention system is ongoing.
  • MEP rough-in of the locker rooms in progress.
  • Piping and wiring to connections to the air handling units in progress.
  • Electrical overhead rough-in in the gym in progress.
  • Wall close-ins on level 2 of sector 1B in progress.
  • Installation of canopy roofing at the main entrance in progress.
  • Painting of classrooms and all CMU walls in progress.
  • Installation of the elevator room in progress. 
  • MEP rough-in in the main mechanical/electrical room in progress.

30-Day Look Ahead:

  • Interior stud wall framing in the locker room is ongoing. 
  • MEP ceiling rough-in in sector 2G is ongoing. 
  • Installation of the site underground utilities is ongoing.
  • Installation of interior door frames is ongoing.
  • Installation of the canopy TPO roofing is ongoing.
  • Painting of 1B and 2A classrooms and all CMU walls is ongoing.
  • Install of electrical generator and HVAC chiller to begin.

COLIN L. POWELL K-8 ACADEMY

Top Row: Roofing and exterior metal panels (exterior northwest view); Classroom – drywall, paint, and ceiling grid installed (interior)
Bottom Row: Corridor – drywall, paint, main duct insulated, and door frames installed (interior); Exterior metal panels and eest entrance (exterior southwest view)

Project Executive: Arland Knipe

Past Month’s Accomplishments:

  • Asphalt paving at the Swan Creek Road widening completed.
  • Installation of the underground stormwater detention system completed.
  • Installation of exterior metal wall panels at the west entrance completed.
  • Installation of storefront frames at the north and south of the 4-story tower completed.
  • Spray fireproofing on level 3 of the 3-story tower completed.
  • In-wall MEP rough-in on levels 2 and 3 of the 4-story tower completed.
  • Hanging drywall on level 1 of the 4-story tower completed.
  • Overhead MEP rough-in on Level 4 of the 4-story tower and on level 2 of the 3-story tower completed.
  • Installation of 4-story tower elevator completed.

Work in Progress:

  • Preparation of interior areas for temporary heating systems in progress.
  • Installation of exterior metal wall panels at the 3-story tower in progress.
  • Overhead MEP rough-in in the auxiliary gym and music rooms and on level 3 of the 3-story tower in progress.
  • In-wall inspections on levels 2 and 3 of the 4-story tower in progress.
  • In-wall MEP rough-in on level 4 of the 4-story tower in progress.
  • Installation of the 3-story tower elevator in progress.
  • Road widening at Fort Washington Road in progress.

30-Day Look Ahead:

  • Installation of storefront frames and glass at the 3-story tower are ongoing. 
  • Spray fireproofing at the west entrance to begin.
  • Installation of exterior metal wall panels to be completed.
  • Interior stud wall framing on levels 2 and 3 of the 3-story tower is ongoing.
  • Installation of the dining/media learning stairs to begin.
  • Installation of kitchen quarry tile to begin.

    DREW-FREEMAN MIDDLE SCHOOL


Top Row: Classroom ceiling grid installation; Exterior generator install on pad
Bottom Row: Toilet rooms ceramic tile installation; Classroom corridor – paint, ceiling grid, and overhead device installation

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Installation of concrete sidewalks in the front of the building completed.
  • Spray fireproofing patching in on level 1 of sectors 1A and 1B completed.
  • Installation of HVAC chiller, electrical generator, and elevator completed.
  • Installation of main and rear entrance doors completed.
  • Installation of exterior windows in the kitchen area of sector 2K.

Work in Progress:

  • Wall close-ins in sector 1B in progress.
  • Installation of the southeast retaining wall in progress.
  • Installation of ceiling grid in sector 1A in progress.
  • Prime and first coat painting in sectors 1A and 1B in progress.
  • Installation of electrical switchgear in progress.

30-Day Look Ahead:

  • Installation of RTUs is ongoing.
  • Installation of refrigerant piping to the walk-in freezer in the sector 2K kitchen is ongoing.
  • Fine grading of ball fields is ongoing.
  • Paving of the basketball court is ongoing.
  • Hanging and finishing of walls throughout sectors 1A and 1B is ongoing.
  • Prime and first coat painting in sectors 1A and 1B is ongoing.

HYATTSVILLE MIDDLE SCHOOL

Top Row: Conference room – drywall, paint, and ceiling grid installed (interior); Corridor – drywall, paint, and bulkheads installed
Bottom Row: Kitchen area – drywall installed (interior); site work for bio ponds (exterior west side view)

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Prime and first coat painting of interior walls on levels 1 and 2 of sector 1B completed.
  • ACT ceiling grid on levels 2 and 3 of sector 1A completed.
  • Fire sprinkler installation on level 4 of sector 1B completed.
  • Drywall close-in on level 3 of sector 1B completed.
  • Electrical in-wall rough-in on levels 3 and 4 of sector 1B completed.
  • Installation of ceiling devices, GRDs, and light fixtures in the sector 1A and 2A  academic classrooms completed.

Work in Progress:

  • Drywall close-in and finishing of interior walls on levels 2 and 3 of sector 1A in progress.
  • Telecom cabling terminations on level 1 of sectors 1A and 1B in progress.
  • Electrical power distribution rough-in on levels 3 and 4 of sector 1B in progress.
  • Sprinkler installation at the gymnasium in sector 2G in progress.
  • Elevator adjusting for a temporary-use inspection in progress.
  • Stone base at the lower parking lot in progress.
  • Underground water line testing and flushing at the north side of site in progress.
  • Undercut and backfill of the bus loop area in progress.

30-Day Look Ahead:

  • MEP, sprinkler, and telecom overhead rough-in, testing, and insulation is ongoing. 
  • Base asphalt paving at the lower lot to continue.
  • Setting of the Pepco transformer and switchgear to begin.
  • One-siding of walls at the kitchen and performance rooms to begin.
  • Prime and first coat painting at the classrooms and corridors in sector 3B to begin.
  • ACT ceiling grid installation at the sector 1B tower is ongoing. 
  • Light fixture and ceiling device installation at the sector 3A tower to begin.
  • VCT flooring installation at sector 1A to begin.
  • Learning Stair installation to begin.

KENMOOR MIDDLE SCHOOL

Top Row: Bus loop undercut and backfill; Classroom corridor: sprinkler head and electrical in wall installation
Bottom Row: Guidance corridor; FF&E casework installation

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • In-wall MEP rough-in in sector 2A completed.
  • Drywall close-in in sector 2B and the sector 2K kitchen completed.
  • Drywall finishing and prime and first coat painting in sector 1A completed.
  • Ceiling grid installation in sector 1B completed.
  • Electrical panelboard connections completed.
  • Overhead ductwork, installation of fire protection and framing the sector 2G gym completed.
  • Elevator cab installation completed.
  • Installation of underground main gas line to the building completed.
  • Kitchen walk-in cooler box installation completed.

Work in Progress:

  • Media bulkhead framing in progress.
  • Elevator cab testing and balancing in progress.
  • Ductwork and piping insulation in the sector 2G gym in progress.
  • Mechanical room rough-in and final connection to electrical equipment in progress.
  • Installation of underground main water line to building in progress.
  • Grading for bus parking lot in progress.
  • Ceiling grid installation in sector 1A in progress.
  • Installation of one-side drywall in sector 2A in progress.
  • GRD drops and connections and installation of light fixtures in sector 1B in progress.
  • Storm pipe MH24 – MH 25 and temporary heat installation in progress.
  • RTU connections to units in progress.

30-Day Look Ahead:

  • Electrical in-wall rough-in in the sector 2G gym to be completed.
  • Bus parking lot curbs, gutters, and asphalt base to be completed.
  • Drywall close-in in sector 2A to begin.
  • Ceiling grid installation, priming, and painting in sector 2B to begin.
  • Hard ceiling inspection and close-in in sector 1A to be completed.
  • Ceiling grid installation in sector 2B to be completed.
  • Light fixtures drop ceiling installation in sector 1A to begin.
  • Bathroom tile on level 1 of the classroom sector to begin.
  • Flooring in sector 1B to begin.
  • Softball field grading to begin.

WALKER MILL MIDDLE SCHOOL

Top Row: Southern service road underground site utility installation; Kitchen hood installation
Bottom Row: Classroom corridor ceiling grid, tile, and overhead device installation; Rooftop view – tubular skylights, RTU unit installation

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Soil nail retaining wall at the back of school site completed.
  • Hanging and finishing of walls on level 2 of sector 1B completed.
  • First delivery of RTUs received.
  • Installation of sanitary line running down service road completed.
  • Ceiling grid installation on level 1 of sector 1A completed.
  • Prime painting of block walls in the sector 2G gym completed.
  • First coat painting of walls on level 1 of sectors 1A and 1B completed.

Work in Progress:

  • Installation of underground site utilities in the west parking lot and service road in progress.
  • Installation of elevator at sector 1 media center in progress.
  • Main mechanical room rough-ins in the sector 2K kitchen in progress.
  • Overhead MEP rough-in on level 2 of sector 1A in progress.
  • Framing of interior walls in the sector 2G gym in progress.
  • Installation of light fixtures on level 1 and prime painting of walls on level 2 of sector 1B in progress.
  • Frame bulkheads at skylight tubes in progress.
  • One-side hanging of drywall on level 2 of sector 1A and the sector 2K kitchen in progress.
  • Overhead MEP rough-in in the sector 2G gym in progress.

30-Day Look Ahead:

  • Installation ceramic tile, flooring, and casework on level 1 of sector 1B to begin.
  • Installation of MEP equipment in ceiling tile on level 1 of sector 1A to begin.
  • Installation of ceiling grid on level 2 of sector 1B to begin.
  • Underground site utilities throughout the project site are ongoing.
  • Insulation, hanging, and finishing of walls on level 2 of sector 1A is ongoing.
  • Elevator adjuster at the sector 1 media center is ongoing.
  • Installation of concrete footers at the entrance canopy to begin.

*Please note: Construction timeframes shown above are subject to change.