Project Construction Updates: February 2022

Project Construction Updates: February 2022

ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:

  • All underslab plumbing and electrical completed.
  • All concrete slabs on grade completed.
  • Erection of steel in the Kitchen and Gym sectors completed.
  • Erection of classroom steel in building sectors 1A and 1B in progress.
  • Form/pour stage ramp/slab and foundation wall damp-roofing and backfill in progress.

30-Day Look Ahead:

  • Building perimeter knee wall framing and AVB at sectors 1A, 2K, and 2G is ongoing.
  • Roof parapet framing for east commons is ongoing.
  • MEP hangers and interior wall layout at sector 1A to begin.
  • Structural steel erection in sectors 1A and 1B to continue.
  • Façade metal panel deliveries to begin.
  • Slab on deck pours at 1A to continue.

DREW-FREEMAN MIDDLE SCHOOL

Project Executive: Christian Broyles 

Past Month’s Accomplishments:

  • Installation of concrete slabs on grade in building sector 2G completed.
  • Installation of concrete building foundations in building sector 2K in progress.
  • Underslab plumbing and electrical in building sector 2K completed.
  • Erection of classroom steel in building sector 1A completed.
  • Erection of classroom steel in building sector 1B in progress.
  • Pouring of concrete foundation walls in building sector 2K in progress.
     

30-Day Look Ahead:

  • Pouring of concrete slabs on grade in building sector 2K to be completed.
  • Knee wall installation in building sectors 1A and 1B is ongoing.
  • Installation of secondary steel in classroom sectors 1A and 1B to continue.
  • Erection of steel in building sector 2G and 2K to continue.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Pouring of sector 1A concrete slab on metal deck (2nd Floor) completed.
  • Steel detailing and secondary steel install at sector 1A in progress.
  • Primary steel erection at 2K in progress.
  • MEP slab rough-in at the sector 1A elevated decks in progress.
  • CMU walls in sector 2G and CMU elevator shaft in progress.
  • Grading turf field in progress.
  • Foundation wall damp-roofing and backfill in progress.
     

30-Day Look Ahead:

  • Building perimeter knee wall framing and AVB at sector 1A is ongoing.
  • Roof parapet framing at sector 1A is ongoing.
  • MEP Hangers and Interior Wall Layout at sector 1A to begin.
  • Structural steel erection in sectors 2K, 2G, and 1B to continue.
  • Façade metal panel deliveries to begin.
  • Concrete slab on deck pours at sector 1A floors 3 and 4 to continue.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Concrete slab on grade in sector 2G and center infill completed.
  • Primary and secondary steel in sector 2K completed.
  • Primary steel in sectors 1A and 1B completed.
  • Pouring of slab on metal deck in sector 1B completed.
  • Secondary steel installation in sectors 1A, 1B, and Infills in progress.
  • Metal decks, MEP prep, and concrete pours in sectors 1A and 1B to continue.
  • Knee wall installation and waterproofing around the perimeter of the building in progress.
     

30-Day Look Ahead:

  • Steel erection of sector 2G and center infill to be completed.
  • Roof Panel Installation and exterior masonry walls in Sector 2K and 1B to begin.
  • Interior layout of critical walls (MEP rooms, bathrooms, corridors) to begin.
  • Main power duct bank run from existing school to new building to begin.
  • MEP hangers and top track in sector 1B first floor to begin.

SOUTHERN AREA K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Foundations and elevator pit at 4-story tower completed.
  • Under slab plumbing and electrical at east and north center areas completed.
  • Preparation for slab on grade pour at east area completed.
  • Monitoring settlement of fill dirt and surcharge dirt on the building pad in progress.
  • Grading of site at the green field and playing court areas in progress.
  • Delivery of steel joists and metal decking in progress.
  • Mobilization of steel erector and crane to site in progress.

30-Day Look Ahead:

  • Pouring of concrete slab on grade at east side to begin.
  • Under slab MEP utilities at 4-story tower to begin.
  • Pouring of concrete slab on grade in gym to begin.
  • Erection of structural steel to begin.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Rough in MEP underground utilities in sector 1A completed.
  • Deliveries of structural steel completed.
  • Pouring of concrete slab on grade in sector 1B completed.
  • Pouring of concrete slab on grade in sector 1A completed.
  • Steel erection in sector 1B in progress.
  • Installation of concrete building foundations and rough in of MEP underground utilities in sector 2K in progress.
  • Installation of concrete building foundations in sector 2G in progress.

30-Day Look Ahead:

  • Detailing of steel in sector 1B to begin.
  • Steel erection in sector 1A to begin.
  • Concrete building foundations in sector 2K to be completed.
  • Pouring of concrete slab on grade in sector 2K to begin.
  • Finish concrete building foundations in sector 2G to be completed.
     

*Please note: Construction timeframes shown above are subject to change.