01 Mar Project Construction Updates: February 2022
ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- All underslab plumbing and electrical completed.
- All concrete slabs on grade completed.
- Erection of steel in the Kitchen and Gym sectors completed.
- Erection of classroom steel in building sectors 1A and 1B in progress.
- Form/pour stage ramp/slab and foundation wall damp-roofing and backfill in progress.
30-Day Look Ahead:
- Building perimeter knee wall framing and AVB at sectors 1A, 2K, and 2G is ongoing.
- Roof parapet framing for east commons is ongoing.
- MEP hangers and interior wall layout at sector 1A to begin.
- Structural steel erection in sectors 1A and 1B to continue.
- Façade metal panel deliveries to begin.
- Slab on deck pours at 1A to continue.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of concrete slabs on grade in building sector 2G completed.
- Installation of concrete building foundations in building sector 2K in progress.
- Underslab plumbing and electrical in building sector 2K completed.
- Erection of classroom steel in building sector 1A completed.
- Erection of classroom steel in building sector 1B in progress.
- Pouring of concrete foundation walls in building sector 2K in progress.
30-Day Look Ahead:
- Pouring of concrete slabs on grade in building sector 2K to be completed.
- Knee wall installation in building sectors 1A and 1B is ongoing.
- Installation of secondary steel in classroom sectors 1A and 1B to continue.
- Erection of steel in building sector 2G and 2K to continue.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Pouring of sector 1A concrete slab on metal deck (2nd Floor) completed.
- Steel detailing and secondary steel install at sector 1A in progress.
- Primary steel erection at 2K in progress.
- MEP slab rough-in at the sector 1A elevated decks in progress.
- CMU walls in sector 2G and CMU elevator shaft in progress.
- Grading turf field in progress.
- Foundation wall damp-roofing and backfill in progress.
30-Day Look Ahead:
- Building perimeter knee wall framing and AVB at sector 1A is ongoing.
- Roof parapet framing at sector 1A is ongoing.
- MEP Hangers and Interior Wall Layout at sector 1A to begin.
- Structural steel erection in sectors 2K, 2G, and 1B to continue.
- Façade metal panel deliveries to begin.
- Concrete slab on deck pours at sector 1A floors 3 and 4 to continue.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Concrete slab on grade in sector 2G and center infill completed.
- Primary and secondary steel in sector 2K completed.
- Primary steel in sectors 1A and 1B completed.
- Pouring of slab on metal deck in sector 1B completed.
- Secondary steel installation in sectors 1A, 1B, and Infills in progress.
- Metal decks, MEP prep, and concrete pours in sectors 1A and 1B to continue.
- Knee wall installation and waterproofing around the perimeter of the building in progress.
30-Day Look Ahead:
- Steel erection of sector 2G and center infill to be completed.
- Roof Panel Installation and exterior masonry walls in Sector 2K and 1B to begin.
- Interior layout of critical walls (MEP rooms, bathrooms, corridors) to begin.
- Main power duct bank run from existing school to new building to begin.
- MEP hangers and top track in sector 1B first floor to begin.
SOUTHERN AREA K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Foundations and elevator pit at 4-story tower completed.
- Under slab plumbing and electrical at east and north center areas completed.
- Preparation for slab on grade pour at east area completed.
- Monitoring settlement of fill dirt and surcharge dirt on the building pad in progress.
- Grading of site at the green field and playing court areas in progress.
- Delivery of steel joists and metal decking in progress.
- Mobilization of steel erector and crane to site in progress.
30-Day Look Ahead:
- Pouring of concrete slab on grade at east side to begin.
- Under slab MEP utilities at 4-story tower to begin.
- Pouring of concrete slab on grade in gym to begin.
- Erection of structural steel to begin.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Rough in MEP underground utilities in sector 1A completed.
- Deliveries of structural steel completed.
- Pouring of concrete slab on grade in sector 1B completed.
- Pouring of concrete slab on grade in sector 1A completed.
- Steel erection in sector 1B in progress.
- Installation of concrete building foundations and rough in of MEP underground utilities in sector 2K in progress.
- Installation of concrete building foundations in sector 2G in progress.
30-Day Look Ahead:
- Detailing of steel in sector 1B to begin.
- Steel erection in sector 1A to begin.
- Concrete building foundations in sector 2K to be completed.
- Pouring of concrete slab on grade in sector 2K to begin.
- Finish concrete building foundations in sector 2G to be completed.
*Please note: Construction timeframes shown above are subject to change.