Project Construction Updates: January 2022

Project Construction Updates: January 2022

ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:

  • 95% of concrete slab on grade in building sectors 1A and 1B complete.
  • Concrete building foundations at building sector 1A complete.
  • Under slab utilities at building sector 1A complete.
  • Concrete slab on grade at sector 1A complete.
  • Pouring of concrete building foundation footings, piers & walls at building sectors 2G and 2K in progress.
  • Rough in under slab utilities at building sector 2G in progress.

30-Day Look Ahead:

  • Pouring of concrete building foundations at sector 2G is ongoing.
  • Rough in under slab utilities at sectors 2K and 2G to continue.
  • Pouring of concrete slab on grade at sectors 2G and 2K is ongoing.

DREW-FREEMAN MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Installation of concrete slab on grade for building sector 1A is complete and 1B is in progress.
  • Phase III of the existing building demolition in progress.
  • Installation of concrete foundation walls/piers/footings in building sector 2G in progress.
  • Rough in under slab plumbing in building sector 2G in progress.
  • Rough in under slab electrical in building sector 2K in progress.
  • Preparation for structural steel crane set up in progress.

30-Day Look Ahead:

  • Continue concrete building foundations for sectors 2G and 2K is ongoing.
  • Demolition of existing building Phase III to be completed.
  • Rough in under slab plumbing and electrical for sectors 2G and 2K is ongoing.
  • Pouring of concrete slabs on grade at sectors 2G and 2K to begin.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Sorting and hauling of existing building demolition debris complete.
  • Pouring of concrete foundations at building sectors 2K, 2G, and 1A complete
  • Concrete slab on grade pours at sector 1A complete.
  • Pouring of concrete building foundation footings, piers and walls at sector 1B in progress.
  • Construction of site access roads and laydown areas underway.
  • Installation of under slab utilities at building sectors 2G and 1B in progress.
  • Structural steel deliveries in progress.

30-Day Look Ahead:

  • Concrete slab on grade pours at sectors 2G and 2K to continue.
  • Under slab utilities at sector 1B to continue.
  • Structural steel erection to begin.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Concrete building foundations in building sectors 2K, 1B and 1A complete.
  • Underground site utilities in building sectors 2K, 1B and 80% of 1A complete.
  • Pouring of concrete slab on grade at sectors 1A, 1B, and 2K ongoing.
  • Elevator pit including walls, waterproofing and dirt backfill complete.
  • Structural steel on site received and shakeout/inventory activities begun.
  • Mobilization activities and assembly of the structural steel erection crane complete.
  • Grading and setup of staging area for the stability piles on the south side of building complete.
  • Site perimeter clearing activities complete.     

30-Day Look Ahead:

  • Underground building site utilities to be completed.
  • Building of concrete foundations at sector 2G and learning stairs to be completed.
  • Pouring of concrete slab on grade in sectors 1A, 1B, and 2G to be completed. 
  • Erecting of structural steel at sectors 1A and 1B to begin.

SOUTHERN AREA K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Grading of building pad complete.
  • Surcharge dirt loading on building pad complete.
  • Temporary power to building pad and construction trailers installed.
  • All remaining tree debris removed from site.
  • Concrete foundations at East side of building in progress.
  • Monitoring settlement of fill dirt and surcharge dirt on the building pad in progress.
  • Installation of MEP under footings and sleeves through foundation walls underway.
  • Import of fill dirt and installation of stone for site parking and laydown areas in progress.

30-Day Look Ahead:

  • Under slab MEP rough-in at East side to begin.
  • Concrete slab on grade at East side to begin.
  • Receive deliveries of structural steel to begin.
  • Grading site at greenfield areas to begin.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Concrete foundations at classroom wing 1B complete.
  • Removal of surcharge dirt at classroom wings 2G and 2K complete.
  • Installation of site haul road and laydown areas in progress.
  • First delivery of steel joists and metal deck received.
  • MEP underground at classroom wing 1B in progress.
  • Pouring of concrete foundation footings, piers & walls at classroom wing 1A in progress.
  • Preparing of building pad in Building Wings 2G and 2K underway.

30-Day Look Ahead:

  • Classroom wing 1A foundations to be completed.
  • Underground MEP at wing 1A to begin.
  • Pouring of concrete slab on grade at wing 1B to begin.
  • Pouring of foundations at wing 2K to begin.
  • Structural steel beams/columns deliveries to be received.