PROJECT CONSTRUCTION UPDATES: July 2022

PROJECT CONSTRUCTION UPDATES: July 2022

ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:

  • MEPF hangers installation and interior wall layout at building sectors 2A and 2B completed.
  • Installation and pouring of concrete stair tread infills at stair 2 completed.
  • Spraying of fireproofing and ceiling hat channel installation at building sector 1B completed.
  • Exterior wall panel installation at building sector 2G completed.
  • Framing out of interior walls on level 1 of building sector 1B completed.
  • Ceiling metal lath installation on level 2 of building sector 1B completed.
  • Underground site storm water infrastructure at parking lot area completed.
  • Interior CMU block walls in the gym completed.
  • MEP above ceiling rough-in and exterior brick installation at building sector 1A completed.
  • Site storm water utilities installation at soccer field completed.
  • Installation of ceiling metal lath, MEPF hangers, and interior wall layout on level 2 of building sector 1B in progress.
  • Installation of site underground sanitary piping in progress.
  • Installation of exterior brick, building foundation wall waterproofing, and backfill at building sector 1B in progress.
  • Spraying of fireproofing ceiling lath at building sector 1A in progress.
  • MEPF rough-in at building sector 1B, east commons, and gym in progress.
  • Installation of TPO roofing at east commons in progress.

30-Day Look Ahead:

  • Interior stud wall framing on level 2 of building sector 1A is ongoing.
  • MEP ceiling rough-in at building sector 1B and level 2 of building sector 1A is ongoing.
  • MEPF hangers installation on level 2 of building sector 1B to be completed.
  • Exterior brick around the perimeter of the building to be completed.
  • Installation of exterior wall panels in building sectors 1A and 1B to continue.
  • Installation of the site underground utilities is ongoing.
  • Installation of TPO roofing at the east and west commons to be completed.

DREW-FREEMAN MIDDLE SCHOOL

Project Executive: Christian Broyles 
Past Month’s Accomplishments:

  • Installation of roof panels in building sectors 1B and 2K completed.
  • Installation of interior CMU block walls in building sector 2K completed.
  • Installation of interior wall framing in building sector 1A completed.
  • Secondary exterior steel erection in building sectors 1A and 1B completed.
  • Installation of site underground storm/sanitary lines on west side of the building completed.
  • Spraying of fireproofing in building sectors 1B and 2G in progress.
  • Installation of interior CMU block walls in building sector 2G in progress.
  • Installation of interior wall framing in building sector 1B in progress.
  • Installation of MEPF in building sectors 1A and 1B in progress.
  • Installation of exterior brick and drywall top out in building sector 1A in progress.
  • Installation of site underground water utility piping to the building in progress.

30-Day Look Ahead:

  • Installation of exterior brick in building sectors 1B and 2K is ongoing.
  • Installation of MEPF in first floor of building sectors 1A and 1B is ongoing.
  • Spraying of fireproofing in building sectors 2G and 2K is ongoing.
  • Installation of MEPF rough-ins and fire protection on level 2 of building sector 1A is ongoing.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Elevator shaft top out at building sector 1B completed.
  • HVAC ductwork risers in building sector 1A tower completed
  • Installation and pouring of concrete stair tread infills at the stair 3 egress in building sector 1A completed.
  • Spraying of fireproofing on the 3rd floor of building sector 1A completed.
  • Exterior metal wall panel installation at building sectors 1A and 2G completed.
  • Roof parapet framing and blocking at building sector 1A completed.
  • Ceiling hat channel installation at building sector 2K completed.
  • Secondary steel installation at building sectors 1B and 2G in progress.
  • Building perimeter knee wall construction and installation of exterior metal wall panels at building sector 2G in progress.
  • Sprinkler installation and electrical overhead rough-in on 1st floor of building sector 1A in progress.
  • Interior wall framing and one-siding drywall on floors 1 and 2 of building sector 1A  in progress.
  • Spraying of fireproofing on floor 2 of building sector 1B in progress.
  • Installation of MEP ceiling hangers and interior stud wall framing floor 1 of building sector 1B in progress.
  • Stair 2 installation at building sector 1A tower in progress.
  • Site underground storm water and water line utilities at south side of building in progress.
  • Interior CMU block wall bracing installation at building sector 2G in progress.
  • Roof parapet framing and blocking in progress.

30-Day Look Ahead:

  • Exterior metal wall panel installation at building sector 2G to begin.
  • MEP overhead rough-in, testing, and insulation is ongoing.
  • Sprinkler installation at Sector 1A tower is ongoing.
  • Overhead HVAC ductwork installation at building sectors 1A and 1B towers is ongoing.
  • Spraying of fireproofing at building sector 1B to continue.
  • TPO roofing installation at building sector 1A is ongoing.
  • Secondary steel installation at building sector 1B tower is ongoing.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Backfill at the perimeter of the building completed.
  • Interior stud wall framing at level 1 of sector 1A and sector 2K completed.
  • Spraying of fireproofing in sectors 2K and 2G completed.
  • Roof panel installation in sector 2G completed.
  • Overhead and in-wall mechanical and plumbing rough-in on level 1 of sector 1B completed.
  • Site underground sanitary utility piping completed.
  • Installation of exterior wall panels at sectors 1A, 2K and 2G in progress.
  • Installation of TPO roofing at sectors 1A, 1B, 2K and 2G in progress.
  • Overhead and in-wall MEP rough-in on level 1 of sector 1A in progress.
  • Installation of electrical raceways ceiling rough-in in sector 1A and level 1 of sector 1B in progress.
  • Installation of overhead MEP rough-in in Sector 2K in progress.
  • Electrical rooms rough-in and installation of windows in progress.

30-Day Look Ahead:

  • Spraying of fireproofing ceiling lath on level 2 of sector 1A and sector 1B to be completed.
  • Interior stud wall framing at sector 1B level 2 to begin.
  • MEP ceiling and wall rough-in in building sector 2K and level 2 of 1B is ongoing.
  • Installation of exterior wall panels in building sectors 1A and 2G is ongoing.
  • Installation of site underground water and storm utilities to begin.

COLIN L. POWELL K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • All concrete slab on grade completed.
  • Steel erection at building sequences 3A and 3B (4-story tower) completed.
  • Metal decking installation at levels 2 and 3 of the 4-story tower completed.
  • Secondary steel erection at building sequence 2 completed.
  • Roofing at building sequence 1 (kitchen and dining areas) completed.
  • Storm utility work at the south parking area completed.
  • Spraying of fireproofing, MEP hangers and ductwork installation, and exterior brick installation in building sequence 1 in progress.
  • Metal decking installation on level 4 of the 4-story Tower in progress.
  • Interior CMU block wall construction at the main gym and stage in progress.
  • Parapet exterior framing and sheathing at building sequence 2 in progress.

30-Day Look Ahead:

  • Construction of retaining wall to begin.
  • Installation of TPO roofing at building sequence 2 to begin. 
  • Concrete slab on metal deck pours at level 2 of the 4-story tower to begin.
  • Steel erection at the 3-story tower to begin.
  • Installation of HVAC ductwork and overhead plumbing in building sequence 1 is ongoing.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Roof panel installation at building sectors 1A and 2G completed.
  • Interior stud wall framing at sector 1B completed.
  • Installation of exterior brick at sector 1B and 2K completed.
  • Wall layout at sector 1A completed.
  • Installation of interior MEP overhead rough in sector 1B in progress.
  • Spraying of fireproofing at building sector 1A in progress.
  • Installation of interior CMU block walls at building sectors 2K and 2G in progress.
  • Installation of exterior wall panels at sector 2K in progress.
  • Installation of CMU support steel at sector 2G in progress.

30-Day Look Ahead:

  • Installation of metal ceiling lath at building sector 1B to begin.
  • Interior wall framing, MEP overhead rough-in, and TPO roof installation at sector 1A to begin.
  • Exterior brick ledge at sector 1A to be completed.
  • Installation of exterior wall panels at sector 1B to be completed.
  • Installation of underground site utilities throughout the project site to begin.
  • Installation of underground water line division valve on Karen Blvd to be completed.

*Please note: Construction timeframes shown above are subject to change.