01 Aug PROJECT CONSTRUCTION UPDATES: July 2022
ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- MEPF hangers installation and interior wall layout at building sectors 2A and 2B completed.
- Installation and pouring of concrete stair tread infills at stair 2 completed.
- Spraying of fireproofing and ceiling hat channel installation at building sector 1B completed.
- Exterior wall panel installation at building sector 2G completed.
- Framing out of interior walls on level 1 of building sector 1B completed.
- Ceiling metal lath installation on level 2 of building sector 1B completed.
- Underground site storm water infrastructure at parking lot area completed.
- Interior CMU block walls in the gym completed.
- MEP above ceiling rough-in and exterior brick installation at building sector 1A completed.
- Site storm water utilities installation at soccer field completed.
- Installation of ceiling metal lath, MEPF hangers, and interior wall layout on level 2 of building sector 1B in progress.
- Installation of site underground sanitary piping in progress.
- Installation of exterior brick, building foundation wall waterproofing, and backfill at building sector 1B in progress.
- Spraying of fireproofing ceiling lath at building sector 1A in progress.
- MEPF rough-in at building sector 1B, east commons, and gym in progress.
- Installation of TPO roofing at east commons in progress.
30-Day Look Ahead:
- Interior stud wall framing on level 2 of building sector 1A is ongoing.
- MEP ceiling rough-in at building sector 1B and level 2 of building sector 1A is ongoing.
- MEPF hangers installation on level 2 of building sector 1B to be completed.
- Exterior brick around the perimeter of the building to be completed.
- Installation of exterior wall panels in building sectors 1A and 1B to continue.
- Installation of the site underground utilities is ongoing.
- Installation of TPO roofing at the east and west commons to be completed.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of roof panels in building sectors 1B and 2K completed.
- Installation of interior CMU block walls in building sector 2K completed.
- Installation of interior wall framing in building sector 1A completed.
- Secondary exterior steel erection in building sectors 1A and 1B completed.
- Installation of site underground storm/sanitary lines on west side of the building completed.
- Spraying of fireproofing in building sectors 1B and 2G in progress.
- Installation of interior CMU block walls in building sector 2G in progress.
- Installation of interior wall framing in building sector 1B in progress.
- Installation of MEPF in building sectors 1A and 1B in progress.
- Installation of exterior brick and drywall top out in building sector 1A in progress.
- Installation of site underground water utility piping to the building in progress.
30-Day Look Ahead:
- Installation of exterior brick in building sectors 1B and 2K is ongoing.
- Installation of MEPF in first floor of building sectors 1A and 1B is ongoing.
- Spraying of fireproofing in building sectors 2G and 2K is ongoing.
- Installation of MEPF rough-ins and fire protection on level 2 of building sector 1A is ongoing.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Elevator shaft top out at building sector 1B completed.
- HVAC ductwork risers in building sector 1A tower completed
- Installation and pouring of concrete stair tread infills at the stair 3 egress in building sector 1A completed.
- Spraying of fireproofing on the 3rd floor of building sector 1A completed.
- Exterior metal wall panel installation at building sectors 1A and 2G completed.
- Roof parapet framing and blocking at building sector 1A completed.
- Ceiling hat channel installation at building sector 2K completed.
- Secondary steel installation at building sectors 1B and 2G in progress.
- Building perimeter knee wall construction and installation of exterior metal wall panels at building sector 2G in progress.
- Sprinkler installation and electrical overhead rough-in on 1st floor of building sector 1A in progress.
- Interior wall framing and one-siding drywall on floors 1 and 2 of building sector 1A in progress.
- Spraying of fireproofing on floor 2 of building sector 1B in progress.
- Installation of MEP ceiling hangers and interior stud wall framing floor 1 of building sector 1B in progress.
- Stair 2 installation at building sector 1A tower in progress.
- Site underground storm water and water line utilities at south side of building in progress.
- Interior CMU block wall bracing installation at building sector 2G in progress.
- Roof parapet framing and blocking in progress.
30-Day Look Ahead:
- Exterior metal wall panel installation at building sector 2G to begin.
- MEP overhead rough-in, testing, and insulation is ongoing.
- Sprinkler installation at Sector 1A tower is ongoing.
- Overhead HVAC ductwork installation at building sectors 1A and 1B towers is ongoing.
- Spraying of fireproofing at building sector 1B to continue.
- TPO roofing installation at building sector 1A is ongoing.
- Secondary steel installation at building sector 1B tower is ongoing.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Backfill at the perimeter of the building completed.
- Interior stud wall framing at level 1 of sector 1A and sector 2K completed.
- Spraying of fireproofing in sectors 2K and 2G completed.
- Roof panel installation in sector 2G completed.
- Overhead and in-wall mechanical and plumbing rough-in on level 1 of sector 1B completed.
- Site underground sanitary utility piping completed.
- Installation of exterior wall panels at sectors 1A, 2K and 2G in progress.
- Installation of TPO roofing at sectors 1A, 1B, 2K and 2G in progress.
- Overhead and in-wall MEP rough-in on level 1 of sector 1A in progress.
- Installation of electrical raceways ceiling rough-in in sector 1A and level 1 of sector 1B in progress.
- Installation of overhead MEP rough-in in Sector 2K in progress.
- Electrical rooms rough-in and installation of windows in progress.
30-Day Look Ahead:
- Spraying of fireproofing ceiling lath on level 2 of sector 1A and sector 1B to be completed.
- Interior stud wall framing at sector 1B level 2 to begin.
- MEP ceiling and wall rough-in in building sector 2K and level 2 of 1B is ongoing.
- Installation of exterior wall panels in building sectors 1A and 2G is ongoing.
- Installation of site underground water and storm utilities to begin.
COLIN L. POWELL K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- All concrete slab on grade completed.
- Steel erection at building sequences 3A and 3B (4-story tower) completed.
- Metal decking installation at levels 2 and 3 of the 4-story tower completed.
- Secondary steel erection at building sequence 2 completed.
- Roofing at building sequence 1 (kitchen and dining areas) completed.
- Storm utility work at the south parking area completed.
- Spraying of fireproofing, MEP hangers and ductwork installation, and exterior brick installation in building sequence 1 in progress.
- Metal decking installation on level 4 of the 4-story Tower in progress.
- Interior CMU block wall construction at the main gym and stage in progress.
- Parapet exterior framing and sheathing at building sequence 2 in progress.
30-Day Look Ahead:
- Construction of retaining wall to begin.
- Installation of TPO roofing at building sequence 2 to begin.
- Concrete slab on metal deck pours at level 2 of the 4-story tower to begin.
- Steel erection at the 3-story tower to begin.
- Installation of HVAC ductwork and overhead plumbing in building sequence 1 is ongoing.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Roof panel installation at building sectors 1A and 2G completed.
- Interior stud wall framing at sector 1B completed.
- Installation of exterior brick at sector 1B and 2K completed.
- Wall layout at sector 1A completed.
- Installation of interior MEP overhead rough in sector 1B in progress.
- Spraying of fireproofing at building sector 1A in progress.
- Installation of interior CMU block walls at building sectors 2K and 2G in progress.
- Installation of exterior wall panels at sector 2K in progress.
- Installation of CMU support steel at sector 2G in progress.
30-Day Look Ahead:
- Installation of metal ceiling lath at building sector 1B to begin.
- Interior wall framing, MEP overhead rough-in, and TPO roof installation at sector 1A to begin.
- Exterior brick ledge at sector 1A to be completed.
- Installation of exterior wall panels at sector 1B to be completed.
- Installation of underground site utilities throughout the project site to begin.
- Installation of underground water line division valve on Karen Blvd to be completed.
*Please note: Construction timeframes shown above are subject to change.