PROJECT CONSTRUCTION UPDATES: June 2022

PROJECT CONSTRUCTION UPDATES: June 2022

ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:

  • MEPF hangers and interior wall layout and fire proofing in building sector 1B completed.
  • Installation of roof panels in building sectors 1A and 1B completed.
  • Forming and pouring of concrete stage and ramp completed.
  • Exterior wall panels in building sector 2K completed.
  • Framing out of interior walls on first floor and ceiling hat channels in building sector 1A completed.
  • Underground site storm water infrastructure at parking lot area completed.
  • Interior CMU block elevator shaft walls completed.
  • Ceiling hat channel installation and MEPF rough-in in sector 1B in progress.
  • Site storm water utilities installation in the soccer field in progress.
  • Interior CMU block walls in building sector 2G in progress.
  • Building foundation wall waterproofing and backfill in progress.
  • MEPF hangers and interior wall layout building in level 2 and fireproofing ceiling lath in sectors 1A and 1B in progress.

30-Day Look Ahead:

  • Installation of hat channel system in building sectors 1A, 1B, and 2K is ongoing.
  • Interior wall framing in building sectors 1B and 2K is ongoing.
  • MEP ceiling rough-in in building sector 1B is ongoing.
  • Installation of MEPF hangers in level 2 of building sectors 1A and 1B to be completed.
  • Interior CMU block walls in building sector 2G to be completed.
  • Exterior brick around the perimeter of the building to be completed.
  • Installation of exterior wall panels in building sector 2G to continue.
  • Installation of site storm utilities to continue. 

DREW-FREEMAN MIDDLE SCHOOL

Project Executive: Christian Broyles 

Past Month’s Accomplishments:

  • Installation of roof panels and fire proofing and framing out of interior walls on first floor in building sector 1A completed.
  • Installation of metal decking and secondary exterior steel in building sectors 2G and 2K completed.
  • Hanger rough-in overhead MEPF in building sectors 1A and 1B completed.
  • Installation of building perimeter knee wall in building sectors 1A, 1B and 2G completed.
  • Installation of secondary steel on building sectors 1A and 1B in progress
  • Installation of fireproofing in building sectors 1B and 2G in progress.
  • Installation of interior CMU block walls in progress.
  • Installation of interior wall framing and MEPF in sector 1A in progress.
  • Installation of interior storm/sanitary lines in progress.

30-Day Look Ahead:

  • Installation of MEPF in first floor and exterior brick in building sectors 1A and 1B is ongoing.
  • Installation of fireproofing in building sectors 2G and 2K is ongoing.
  • Installation of interior CMU block walls to continue.
  • Installation of roof panels in building sector 1B and 2K is ongoing.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Interior CMU block walls and ceiling hat channel installation for fireproofing at sector 2K completed.
  • All concrete slab pours on metal deck floors at sector 1B completed.
  • Steel for entrance canopy completed.
  • Fireproofing at 1st and 2nd floors of building sector 1A completed.
  • Metal panel roof at building sector 2G completed.
  • Underground telecom duct bank installation at west side of site completed.
  • Secondary steel install at building sectors 1B, 2G, and 2K in progress.
  • Building perimeter knee wall construction at building sectors 2G and 2K in progress.
  • Building foundation wall waterproofing and backfill in progress.
  • MEPF hangers and interior wall construction at building sector 1A (floors 1-3) in progress.
  • Interior wall framing and one-siding at sector 1A (Floors 1-2) in progress.
  • Spray fireproofing at building sector 1A (Floor 3) and 1B (Floor 1) in progress.
  • Storm water utilities at south side of building in progress.
  • Installation of stair 3 in progress.
  • CMU bracing installation at building sector 2G in progress.
  • Roof parapet framing and blocking in progress.

30-Day Look Ahead:

  • Exterior metal wall panel installation at building sector 2K to begin.
  • MEPF hanger installation at building sectors 1A and1B is ongoing.
  • Installation of HVAC ductwork at building sector 1A (2nd and 3rd floors) to continue.
  • Installation of interior metal stairs (Stair 2) to begin.
  • Fireproofing at 1B sector to continue.
  • TPO roof installation to begin.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Brick masonry walls and backfill at the perimeter of the building completed.
  • Ceiling hat channel and purlin bracing work and ceiling lath installation in 2K
    completed.
  • Interior wall framing in level 1 of sector 1B completed.
  • 70% of interior wall framing in level 1 of sector 1A completed.
  • All MEPF hangers on sector 1A and second level of sector 1B completed.
  • Fireproofing in sector 1B level 1, Sector 2G completed. 
  • Fireproofing in Sector 2K in progress.

30-Day Look Ahead:

  • Installation of fireproofing lath system in building sectors 1A (level 2), 1B (level2), and 2K is ongoing.
  • Interior wall framing in building sectors 1A and 2K is ongoing.
  • MEP ceiling and wall rough-in in building sectors 1B (level 2) and 2K is ongoing. 
  • Interior CMU block walls and installation of the roof panels in building sector 2G to be completed.
  • Installation of exterior wall panels in building sectors 1A, 1B, and 2K to continue.
  • Installation of site sanitary sewer utility to be completed.

SOUTHERN AREA K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Concrete slab on grade at 4-story tower completed.
  • Concrete building foundations and under slab utilities at 3-story tower completed.
  • Steel erection at building sequence 2B (North Center area), 3A and 3B (4-story tower) completed.
  • Metal roof decking at building sequence 2A and 2B completed.
  • Secondary steel at building sequence 1 completed.
  • Storm utility work along west side of building pad completed.
  • Concrete slab on grade at 3-story tower in progress.
  • Steel erection and metal decking at the 4-story tower at building sequence 3 in progress. 
  • Secondary steel at building sequence 2 in progress.
  • Exterior knee wall framing and sheathing in progress.
  • MEP hangers install in sequence 1 in progress.

30-Day Look Ahead:

  • Interior CMU block wall construction to begin.
  • TPO roofing installation at building sequence 1 to begin.
  • Concrete slab on deck at 4-story tower to begin.
  • Steel erection at 3-story tower to begin.
  • Stabilization of playfields to be completed.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Installation of roof panels building and perimeter knee wall installation at building sectors 1B and 2K completed.
  • Secondary steel installation in building sector 1A completed.
  • Primary and secondary steel installation in building sector 2G completed.
  • Fireproofing on first floor of building sector 1B completed.
  • Building perimeter knee wall installation in building sectors 1A and 2G in progress.
  • Installation of interior MEP overhead rough-in in building sector 1B in progress.
  • Interior wall framing at building sector 1B in progress.
  • Interior wall layout building, fireproofing, and installation of roof panels at building sector 1A in progress.
  • Installation of CMU at building sector 2K and elevator shaft in progress.

30-Day Look Ahead:

  • Installation of roof panels at building sector 1A to be completed.
  • Installation of roof panels at building sector 2G to be completed.
  • Exterior brick walls and installation of ceiling metal lath in building sector 1B to begin.
  • Exterior wall panels building sector 1B & 1A to begin.
  • Installation of CMU in building sector 2G to begin.

*Please note: Construction timeframes shown above are subject to change.