01 Jun PROJECT CONSTRUCTION UPDATES: May 2022
ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Building perimeter exterior knee wall framing and MEPF hangers at building sectors 1A and 1B completed.
- Interior CMU block walls in the kitchen area completed.
- Interior wall layout building and elevated concrete deck pours at sector 1B completed.
- Interior CMU block walls in elevator shaft and sector 2G in progress.
- Site storm water utilities installation in progress.
- Pouring of concrete stage ramp in progress.
- Building foundation wall waterproofing and backfill in progress.
30-Day Look Ahead:
- Installation of hat channel system and interior wall framing in building sectors 1A, 1B, and 2K is ongoing.
- MEP ceiling rough-in in building sector 1B is ongoing.
- MEPF hanger installation and roof panel installation in building sectors 1A and 1B to be completed.
- Interior CMU block walls in building sector 2G to be completed.
- Exterior brick around the perimeter of the building to be completed.
- Exterior wall panel installation in building sectors 2K and 2G is ongoing.
- Installation of the site storm utility to be completed.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles Past Month’s Accomplishments:
- Steel erection in building sector 2K completed.
- Installation of metal decking in building sector 1B completed.
- All elevated concrete decks at sector 1 completed.
- Installation of roof panels in building sector 2G completed.
- Installation of building perimeter knee wall in building sectors 1A, 1B and 2G in progress.
- Installation of secondary steel and top and bottom interior wall track in building sectors 1A and 1B in progress.
- Installation of secondary exterior steel in building sectors 2G and 2K in progress.
- Rough in overhead MEPF in sectors 1A and 1B in progress.
- Installation of fireproofing in building sector 1A in progress.
30-Day Look Ahead:
- Installation of exterior brick in building sector 1A is ongoing.
- Installation of interior CMU block walls is ongoing.
- Installation of fireproofing, drywall framing, roof panels, and interior storm/sanitary lines in building sectors 1A and 1B is ongoing.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Interior CMU block walls at stage completed.
- Concrete pouring of stage and stairs at gym completed.
- Primary steel erection at building sector 1B completed.
- Building perimeter knee wall construction and secondary steel installation at building sector 1A completed.
- Metal panel roof at building sector 2K completed.
- Secondary steel installation and building perimeter knee wall construction at building sector 2K in progress.
- Installation of interior hat channel and MEPF hangers at building sector 2K in progress.
- Building foundation wall waterproofing and backfill in progress.
- MEPF Hangers, interior wall construction, and fireproofing at building sector 1A in progress.
- Storm water utilities at SW corner in progress.
30-Day Look Ahead:
- Exterior metal wall panel installation at building sector 1A to begin.
- MEPF hanger installation, interior wall framing, and one-siding with drywall in building sector 1A is ongoing.
- Installation of HVAC ductwork at 1st floor of building sector 1A to begin.
- Installation of interior metal stairs to begin.
- CMU bracing installation at building sector 2G is ongoing.
- Underground telecom ductbank installation at west side of site is ongoing.
- Roof parapet framing and blocking to continue.
- Concrete slab on metal deck pours at floors 2-4 in sector 1B to continue.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- All secondary steel except for the canopy completed.
- Installation of the roof panels in building sectors 1A, 1B, and 2K completed.
- Fireproofing on level 1 of building sector 1B completed.
- MEPF hangers on level 1 of building sectors 1A and 1B and sector 2K completed.
- Interior CMU block walls in building sector 2K completed.
- Building perimeter knee wall installation completed.
- Fireproofing on level 1 of building sector 1A in progress.
- Interior hat channel and purlin bracing work in building sectors 1B and 2K in progress.
- Interior MEP rough-in and interior wall framing on level 1 of building sector 1B in progress.
- Interior CMU block walls in building sector 2G in progress.
- Exterior brick install at building sector 1B in progress.
- MEPF hangers on level 2 of building sector 1B in progress.
- Fireproofing in building sector 1A in progress.
30-Day Look Ahead:
- Fireproofing of lath system and interior wall framing in building sectors 1A, 1B, and 2K is ongoing.
- MEP ceiling rough-in in building sector 2K is ongoing.
- MEPF hangers installation in building sectors 1A and 1B to be completed.
- Interior CMU block walls and installation of roof panels in building sector 2G to be completed.
- Installation of hat channel in building sector 1A to be completed.
- Exterior brick installation to be completed.
- Installation of exterior wall panels in building sectors 1B and 2K is ongoing.
- Installation of site sanitary sewer utility to be completed.
SOUTHERN AREA K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Removal of surcharge at 3-story tower completed.
- Concrete slab on grade at north center area completed.
- Concrete building foundations at west entrance area completed.
- Steel erection at SEQ #1 (east area) completed.
- Steel erection at SEQ #2A (north center area) completed.
- Sewer line work at Emerald Hill Drive completed.
- Concrete slab on grade at 4-story tower in progress.
- Concrete building foundations at 3-story tower in progress.
- Metal roof decking at SEQ #1 (east area) in progress.
- Steel erection at SEQ #2B (north center area) in progress.
- Storm water utility work at south parking area in progress.
30-Day Look Ahead:
- Steel erection at SEQ #3 (4-story tower) to begin.
- Concrete slab on grade at 4-story tower to be completed.
- Installation of metal roof decking at SEQ #2 (north center) to begin.
- Building perimeter knee wall construction (east) to begin.
- Interior CMU block wall construction to begin.
- TPO roofing installation at SEQ #1 to begin.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Steel erection and detailing of steel in building sector 1A completed.
- Secondary steel in building sector 1B completed.
- Steel erection, detailing, and secondary steel in building sector 2K completed.
- Concrete slab on grade at building sector 2G completed.
- Elevated concrete slabs at building sectors 1A and 1B completed.
- Soil verification nails for retaining wall completed.
- Building perimeter knee wall installation building sector 1B in progress.
- Installation of interior MEP hangers at building sectors 1A and 1B in progress.
- Interior wall layout and installation of roof panels at building sector 1B in progress.
- Installation of roof purlin framing at building sector 1A in progress.
30-Day Look Ahead:
- Installation of roof panels at building sector 1B to be completed.
- Installation of roof panels at building sector 1A to continue.
- Construction of exterior wall panels at building sectors 1A and 1B to begin.
- Primary and secondary steel at building sector 2G to be completed.
- Interior MEP hangers at first floor of sector 1A to be completed.
- Fireproofing at first floor of building sectors 1A and 1B to begin.
- Installation of roof panels at building sector 2K to begin.
*Please note: Construction timeframes shown above are subject to change.