PROJECT CONSTRUCTION UPDATES: NOVEMBER 2022

PROJECT CONSTRUCTION UPDATES: NOVEMBER 2022

SONIA SOTOMAYOR MIDDLE SCHOOL AT ADELPHI

Project Executive: Christian Broyles

Past Month’s Accomplishments:

  • MEP rough-ins in sector 2K completed.
  • Drywall close-in on level 2 of sector 1A completed.
  • Installation of the entrance canopy steel completed.
  • Retaining wall at the northeast loading dock completed.
  • Installation of the storm water detention system completed.
  • Installation of the electrical switchgear completed.
  • ACT ceiling grid on level 1 of sector 1A completed.
  • Site underground water piping completed.

Work In Progress:

  • Site underground storm water piping in progress.
  • MEP rough-ins in sectors 2K and 2G in progress.
  • Installation of interior door frames on level 2 of sectors 1A and 1B in progress.
  • Electrical in wall rough-ins on level 1 of sector 2K in progress.
  • Wall close ins on level 2 of sector 1B in progress.
  • Installation of the main entrance canopy roofing in progress.
  • Installation of building elevator in progress.

30-Day Look Ahead:

  • Interior stud wall framing in sector 2G is ongoing.
  • MEP ceiling rough-ins in sectors 2K and 2G are ongoing.
  • Installation of the site underground utilities is ongoing.
  • Installation of interior door frames is ongoing.
  • Installation of the canopy steel structure and TPO roofing is ongoing.
  • Painting of classrooms is sectors 1A and 1B and all CMU walls is ongoing.
  • Installation of electrical generator and HVAC chiller to begin.

COLIN L. POWELL K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Exterior metal wall panels at the 4-story tower completed. 
  • Installation of storefront frames and glazing at the east and north areas completed.
  • Installation of all exterior brick masonry and RTU roof curbs completed. 
  • Spray fireproofing on level 2 of the 3-story tower completed.
  • Overhead MEP rough-ins on level 1 of the 3-story tower completed.
  • Hanging of drywall in the dining area completed.

Work in Progress:

  • Installation of exterior metal wall panels at the 3-story tower in progress.
  • Overhead MEP rough-ins in the auxiliary gym, music rooms, and on level 4 of the 4-story tower in progress.
  • In-wall inspections on levels 1 and 2 and in-wall MEP rough-ins on level 3 of the 4-story tower in progress.
  • Installation of the 4-story tower elevator in progress.
  • Road widening at Ft. Washington Road and Swan Creek Road in progress.
  • Installation of stormwater detention system in progress.

30-Day Look Ahead:

  • Installation of storefront frames and glass at the 4-story tower to begin.
  • Spray fireproofing on level 3 of the 3-story tower to begin.
  • Asphalt paving at Swan Creek Road widening to begin.
  • Overhead MEP rough-ins on level 2 of the 4-story tower to continue.
  • Installation of exterior metal wall panels and hollow metal door frames is ongoing.
  • Interior stud wall framing on level 4 of the 4-story tower is ongoing.

DREW-FREEMAN MIDDLE SCHOOL



Project Executive: Christian Broyles 
Past Month’s Accomplishments:

  • Completed interior stud wall framing in sector 2K and 2G
  • Close-in of all interior walls on level 1 and one-side drywall on level 2 of sectors 1A and 1B completed.
  • Priming and painting on level 1 of sector 1A completed.
  • Installation of high bay skylight tubes and all exterior window installation completed.
  • Fire sprinkler rough-ins in sector 2K completed.
  • Concrete curbs and gutters and base paving of all parking lots and the loading dock completed.



Work in Progress:

  • Overhead MEP rough-ins on level 2 and finishing of drywall throughout sector 1B in progress.
  • Priming and painting of block walls in sectors 1B and 2G in progress.
  • Installation of bio-filtration structures and mechanical room MEP fit out in progress.
  • Ceiling grid on level 1 of sectors 1A and 1B in progress.



30-Day Look Ahead:

  • Installation of light fixtures on level 1 of sector 1A to begin.
  • Insulating and closing of interior walls on level 2 of sector 1 to begin.
  • Priming and painting and installation of ceiling grid on level 1 of sector 1B to begin.
  • Rough-in fire protection in sector 2G and on level 2 of sector 1 is ongoing.
  • Installation of ceramic tile in restrooms on level 1 of sector 1 to begin.
  • Pouring of concrete sidewalks is ongoing.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Prime and first coat painting of interior walls on levels 1 – 3 of sector 1A completed.
  • ACT ceiling grid on level 1 of sector 1A completed.
  • Fire sprinkler installation and electrical in wall rough-in on level 3 of sector 1B completed.
  • Electrical in wall rough-ins, interior stud wall framing, and one-siding drywall on level 4 of sector 1B completed.
  • Removal of unforeseen underground fuel tank completed.
  • Drywall close in on levels 1 and 2 of sector 1B completed.
  • Trim out of exterior metal panels, gutters, and downspouts at sectors 2G and 2K completed.
  • Concrete curbs and gutters at lower parking lot completed.
  • Water testing at exterior storefronts completed.

Work in Progress:

  • Drywall close-in and finishing of interior walls at on levels 2 and 3 of sector 1A in progress.
  • Electrical in wall rough-ins on levels 3 and 4 and electrical power distribution rough-ins on levels 2 and 3 of sector 1B in progress.
  • Telecom cabling installation on level 4 of sectors 1A and 1B in progress.
  • Sprinkler installation in the gymnasium in sector 2G in progress.
  • Elevator installation and MEP work in elevator shaft in progress.
  • Stone base at the lower parking lot and undercut and backfill of the bus loop area in progress.
  • Underground water line tie-in at north side of site in progress.

30-Day Look Ahead:

  • MEP, sprinkler, and telecom overhead rough-ins, testing, and insulation are ongoing.
  • Base asphalt paving at the lower lot to begin.
  • Rough-ins at main mechanical and electrical rooms are ongoing.
  • One-siding walls at kitchen and performance rooms to begin.
  • Prime paint and first coat at classrooms and corridors in sector 1B to begin.
  • ACT ceiling grid installation at sector 1A tower is ongoing.
  • Light fixture and ceiling device installation at sector 1A tower to begin.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • In-wall MEP rough-in in sector 2B completed.
  • Drywall close ins in sectors 1A and 2K completed.
  • Drywall finishing in sector 1A completed.
  • Hardware delivery received.
  • Prime and first coat paint in sector 1B completed.
  • Interior door frame installation completed.
  • Installation of exterior aluminum storefront entrances completed.
  • BGE transformer and final connection and electrical room feeder cable pulls completed.

Work in Progress:

  • MEP in-wall rough-in sector 2A and ceiling grid installation in sector 1B in progress.
  • Elevator cab installation in progress.
  • Overhead ductwork and ductwork and piping insulation in sector 2G in progress. 
  • Mechanical room rough-in and final connection to electrical equipment in progress.
  • Main electrical room buildout and media bulkhead framing in progress.
  • Installation of underground main water and gas lines to building in progress.
  • Grading of bus parking lot in progress.

30-Day Look Ahead:

  • Electrical in wall rough-ins in sector 2B to be completed.
  • Installation of underground storm pipes MH 24 – MH 25 – MH 27 to begin.
  • Temporary heat installation to begin.
  • Asphalt base paving at bus parking lot to begin.
  • Drywall close-in in sector 2B to begin.
  • Priming and painting in sector 1A to begin.
  • Hard ceiling inspection and close-in sector 1B to be completed.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Installation of stairs 1 and 3 completed.
  • Interior MEP in-wall rough-ins at Sector 2K and on level 2 of sectors 1A and 1B completed.
  • Installation of storefront doors at all of exterior completed.
  • Hanging of one side drywall and insulation inspection on level 2 of sector 1B completed.
  • Installation of ACT ceiling grid and first coat paint walls on level 1 of sector 1B completed.
  • Prime painting of walls on level 1 of sector 1A first floor completed.
  • Ductwork in the high media area of sector 1 completed.
  • Caulking of exterior windows completed.
  • Stormtech detention system in west parking lot completed.

Work in Progress:

  • Interior MEP overhead rough ins on level 2 of sector 1A in progress.
  • Construction of soil nail retaining wall at back of school site in progress.
  • Installation of underground site utilities in west parking lot and service road in progress.
  • Installation of elevator at the sector 1 media center in progress.
  • Main mechanical room rough-ins in the sector 2K kitchen in progress.
  • Hanging and finishing of walls on level 2 of sector 1B in progress.
  • Overhead MEP rough-ins on level 2 of sector 1A in progress.
  • Framing of interior walls in the sector 2G gym in progress.

30-Day Look Ahead:

  • Installation of light fixtures on level 1 of sector 1B to begin.
  • Installation of underground site utilities throughout the project site is ongoing.
  • First coat interior paint and ceiling grid installation on level 1 of sector 1A to begin.
  • Installation of soil nail retaining wall to be completed.
  • Hanging and finishing of walls and prime paint on level 2 of Sector 1B is ongoing.
  • Elevator adjuster at sector 1 media center to begin. 
  • One side hang walls in the sector 2K kitchen to begin.

*Please note: Construction timeframes shown above are subject to change.