01 Dec PROJECT CONSTRUCTION UPDATES: NOVEMBER 2022
SONIA SOTOMAYOR MIDDLE SCHOOL AT ADELPHI

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- MEP rough-ins in sector 2K completed.
- Drywall close-in on level 2 of sector 1A completed.
- Installation of the entrance canopy steel completed.
- Retaining wall at the northeast loading dock completed.
- Installation of the storm water detention system completed.
- Installation of the electrical switchgear completed.
- ACT ceiling grid on level 1 of sector 1A completed.
- Site underground water piping completed.
Work In Progress:
- Site underground storm water piping in progress.
- MEP rough-ins in sectors 2K and 2G in progress.
- Installation of interior door frames on level 2 of sectors 1A and 1B in progress.
- Electrical in wall rough-ins on level 1 of sector 2K in progress.
- Wall close ins on level 2 of sector 1B in progress.
- Installation of the main entrance canopy roofing in progress.
- Installation of building elevator in progress.
30-Day Look Ahead:
- Interior stud wall framing in sector 2G is ongoing.
- MEP ceiling rough-ins in sectors 2K and 2G are ongoing.
- Installation of the site underground utilities is ongoing.
- Installation of interior door frames is ongoing.
- Installation of the canopy steel structure and TPO roofing is ongoing.
- Painting of classrooms is sectors 1A and 1B and all CMU walls is ongoing.
- Installation of electrical generator and HVAC chiller to begin.
COLIN L. POWELL K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Exterior metal wall panels at the 4-story tower completed.
- Installation of storefront frames and glazing at the east and north areas completed.
- Installation of all exterior brick masonry and RTU roof curbs completed.
- Spray fireproofing on level 2 of the 3-story tower completed.
- Overhead MEP rough-ins on level 1 of the 3-story tower completed.
- Hanging of drywall in the dining area completed.
Work in Progress:
- Installation of exterior metal wall panels at the 3-story tower in progress.
- Overhead MEP rough-ins in the auxiliary gym, music rooms, and on level 4 of the 4-story tower in progress.
- In-wall inspections on levels 1 and 2 and in-wall MEP rough-ins on level 3 of the 4-story tower in progress.
- Installation of the 4-story tower elevator in progress.
- Road widening at Ft. Washington Road and Swan Creek Road in progress.
- Installation of stormwater detention system in progress.
30-Day Look Ahead:
- Installation of storefront frames and glass at the 4-story tower to begin.
- Spray fireproofing on level 3 of the 3-story tower to begin.
- Asphalt paving at Swan Creek Road widening to begin.
- Overhead MEP rough-ins on level 2 of the 4-story tower to continue.
- Installation of exterior metal wall panels and hollow metal door frames is ongoing.
- Interior stud wall framing on level 4 of the 4-story tower is ongoing.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Completed interior stud wall framing in sector 2K and 2G
- Close-in of all interior walls on level 1 and one-side drywall on level 2 of sectors 1A and 1B completed.
- Priming and painting on level 1 of sector 1A completed.
- Installation of high bay skylight tubes and all exterior window installation completed.
- Fire sprinkler rough-ins in sector 2K completed.
- Concrete curbs and gutters and base paving of all parking lots and the loading dock completed.
Work in Progress:
- Overhead MEP rough-ins on level 2 and finishing of drywall throughout sector 1B in progress.
- Priming and painting of block walls in sectors 1B and 2G in progress.
- Installation of bio-filtration structures and mechanical room MEP fit out in progress.
- Ceiling grid on level 1 of sectors 1A and 1B in progress.
30-Day Look Ahead:
- Installation of light fixtures on level 1 of sector 1A to begin.
- Insulating and closing of interior walls on level 2 of sector 1 to begin.
- Priming and painting and installation of ceiling grid on level 1 of sector 1B to begin.
- Rough-in fire protection in sector 2G and on level 2 of sector 1 is ongoing.
- Installation of ceramic tile in restrooms on level 1 of sector 1 to begin.
- Pouring of concrete sidewalks is ongoing.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Prime and first coat painting of interior walls on levels 1 – 3 of sector 1A completed.
- ACT ceiling grid on level 1 of sector 1A completed.
- Fire sprinkler installation and electrical in wall rough-in on level 3 of sector 1B completed.
- Electrical in wall rough-ins, interior stud wall framing, and one-siding drywall on level 4 of sector 1B completed.
- Removal of unforeseen underground fuel tank completed.
- Drywall close in on levels 1 and 2 of sector 1B completed.
- Trim out of exterior metal panels, gutters, and downspouts at sectors 2G and 2K completed.
- Concrete curbs and gutters at lower parking lot completed.
- Water testing at exterior storefronts completed.
Work in Progress:
- Drywall close-in and finishing of interior walls at on levels 2 and 3 of sector 1A in progress.
- Electrical in wall rough-ins on levels 3 and 4 and electrical power distribution rough-ins on levels 2 and 3 of sector 1B in progress.
- Telecom cabling installation on level 4 of sectors 1A and 1B in progress.
- Sprinkler installation in the gymnasium in sector 2G in progress.
- Elevator installation and MEP work in elevator shaft in progress.
- Stone base at the lower parking lot and undercut and backfill of the bus loop area in progress.
- Underground water line tie-in at north side of site in progress.
30-Day Look Ahead:
- MEP, sprinkler, and telecom overhead rough-ins, testing, and insulation are ongoing.
- Base asphalt paving at the lower lot to begin.
- Rough-ins at main mechanical and electrical rooms are ongoing.
- One-siding walls at kitchen and performance rooms to begin.
- Prime paint and first coat at classrooms and corridors in sector 1B to begin.
- ACT ceiling grid installation at sector 1A tower is ongoing.
- Light fixture and ceiling device installation at sector 1A tower to begin.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- In-wall MEP rough-in in sector 2B completed.
- Drywall close ins in sectors 1A and 2K completed.
- Drywall finishing in sector 1A completed.
- Hardware delivery received.
- Prime and first coat paint in sector 1B completed.
- Interior door frame installation completed.
- Installation of exterior aluminum storefront entrances completed.
- BGE transformer and final connection and electrical room feeder cable pulls completed.
Work in Progress:
- MEP in-wall rough-in sector 2A and ceiling grid installation in sector 1B in progress.
- Elevator cab installation in progress.
- Overhead ductwork and ductwork and piping insulation in sector 2G in progress.
- Mechanical room rough-in and final connection to electrical equipment in progress.
- Main electrical room buildout and media bulkhead framing in progress.
- Installation of underground main water and gas lines to building in progress.
- Grading of bus parking lot in progress.
30-Day Look Ahead:
- Electrical in wall rough-ins in sector 2B to be completed.
- Installation of underground storm pipes MH 24 – MH 25 – MH 27 to begin.
- Temporary heat installation to begin.
- Asphalt base paving at bus parking lot to begin.
- Drywall close-in in sector 2B to begin.
- Priming and painting in sector 1A to begin.
- Hard ceiling inspection and close-in sector 1B to be completed.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of stairs 1 and 3 completed.
- Interior MEP in-wall rough-ins at Sector 2K and on level 2 of sectors 1A and 1B completed.
- Installation of storefront doors at all of exterior completed.
- Hanging of one side drywall and insulation inspection on level 2 of sector 1B completed.
- Installation of ACT ceiling grid and first coat paint walls on level 1 of sector 1B completed.
- Prime painting of walls on level 1 of sector 1A first floor completed.
- Ductwork in the high media area of sector 1 completed.
- Caulking of exterior windows completed.
- Stormtech detention system in west parking lot completed.
Work in Progress:
- Interior MEP overhead rough ins on level 2 of sector 1A in progress.
- Construction of soil nail retaining wall at back of school site in progress.
- Installation of underground site utilities in west parking lot and service road in progress.
- Installation of elevator at the sector 1 media center in progress.
- Main mechanical room rough-ins in the sector 2K kitchen in progress.
- Hanging and finishing of walls on level 2 of sector 1B in progress.
- Overhead MEP rough-ins on level 2 of sector 1A in progress.
- Framing of interior walls in the sector 2G gym in progress.
30-Day Look Ahead:
- Installation of light fixtures on level 1 of sector 1B to begin.
- Installation of underground site utilities throughout the project site is ongoing.
- First coat interior paint and ceiling grid installation on level 1 of sector 1A to begin.
- Installation of soil nail retaining wall to be completed.
- Hanging and finishing of walls and prime paint on level 2 of Sector 1B is ongoing.
- Elevator adjuster at sector 1 media center to begin.
- One side hang walls in the sector 2K kitchen to begin.
*Please note: Construction timeframes shown above are subject to change.