01 Oct PROJECT CONSTRUCTION UPDATES: SEPTEMBER 2022
ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Spray fireproofing, installation of exterior metal wall panels, and MEP rough-in at various levels of sector 2K completed.
- Underground sanitary piping installation at the south connector completed.
- Curb and gutter installation at the vehicular parking area completed.
- Drywall close-in on level 1 of sector 1A completed.
- Building foundation wall waterproofing and backfill at sector 1B completed.
Work In Progress:
- Site underground storm water piping and grading of parking lot in progress.
- Spray fireproofing in the connector area in progress.
- MEPF rough-in in building sectors 1B and 2K, West Commons, and the Gym in progress.
- Installation of exterior windows and electrical in wall rough-in at sector 1B in progress.
- Installation of interior door frames on level 1 of sectors 1A and 1B in progress.
30-Day Look Ahead:
- Interior stud wall framing in sectors 2K and 2G is ongoing.
- MEP ceiling and wall rough-ins in sectors 1A, 1B, and 2K to continue.
- Installation of the site underground utilities to continue.
- Detailing of TPO roof and installation of exterior windows and interior door frames are ongoing.
COLIN L. POWELL K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- All remaining concrete slabs on metal deck completed.
- Secondary steel girt framing at the 4-story tower completed.
- Spray fireproofing and overhead MEP rough-in on various levels of the 4-story tower completed.
- In-wall inspections at the kitchen area completed.
- Curbs, gutters, and sidewalks at the west parking area completed.
Work in Progress:
- Secondary steel and spray fireproofing in the 3-story tower in progress.
- TPO Roofing and overhead MEP rough-ins at the 4-story tower in progress.
- Installation of exterior metal wall panels in building sector 2 in progress.
- Interior CMU block wall construction at the aux gym, dance, and choir rooms in progress.
- Hanging and finishing of drywall in the kitchen areas in progress.
30-Day Look Ahead:
- Spray fireproofing, interior stud wall framing, and overhead MEP rough-ins on various levels of the 4-story tower to begin and continue.
- Asphalt paving at the west parking and access road to begin.
- Installation of exterior metal wall panels to continue
- Curb and gutter construction at the east parking area to begin.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Drywall top out in sector 1B completed.
- All exterior brick in sectors 1 and 2 completed.
- Installation of exterior windows in sectors 1A and 1B completed.
- In-wall blocking and spray fireproofing on various levels of sector 1A completed.
- Exterior metal wall panels in sector 2K completed.
Work in Progress:
- Installation of window framing and exterior windows in building sector 2K in progress.
- Stud wall framing on level 2 of building sector 1A in progress.
- Ductwork rough-ins in building sectors 1A and 1B in progress.
30-Day Look Ahead:
- Installation of stairs 1 and 3 is ongoing.
- Installation of one-side interior drywall in sector 1B to continue.
- Installation of exterior windows and MEPF rough-ins in building sector 2K is ongoing.
- Fire sprinkler rough-ins throughout building sector 1 to continue.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Exterior metal panel installation at sectors 1B and 2G completed.
- Underground sanitary tie in at Oliver Street completed.
- Entrance canopy AVB completed.
- Exterior window installation and caulking and metal ceiling lath installation at sector 2G completed.
- In-wall MEP rough-ins on various levels of sector 1A completed.
- Installation of underground grease interceptor at north site completed.
Work in Progress:
- Trim out of exterior metal panels and gutters and downspouts in sectors 2G and 2K in progress.
- Drywall one-siding interior walls, interior door frame installation, and electrical power distribution rough-ins in sector 1A in progress.
- Fire sprinkler installation, electrical in wall rough-ins, and interior stud wall framing and one-siding drywall in sector 1B in progress.
- Telecom cabling installation in sectors 1A and 1B in progress.
- Grading and undercutting of the lower parking lot in progress.
- Underground site utilities and gas utilities throughout the site in progress.
30-Day Look Ahead:
- MEP, sprinkler, and telecom overhead rough-in, testing, and insulation is ongoing.
- Interior paint at back of house spaces to begin.
- Curb and gutter construction and base asphalt paving at lower lot to begin.
- Mechanical and electrical room rough-ins to begin.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Exterior window installation at sector 2K completed.
- Construction of exterior electrical transformer pad completed.
- Installation of underground chilled water piping, interior building gas line, and exterior metal panels completed.
- In-wall MEP rough-ins in sectors 1A and 1B completed.
- One side drywall in sector 1B completed.
- All stairs except for main learning stairs completed.
- Underground sanitary line connection from kitchen to grease interceptor completed.
Work in Progress:
- Trim, gutters, and downspouts around exterior building perimeter in progress.
- Overhead ductwork and piping insulation in progress,
- Electrical room rough-ins in sector 2K in progress.
- Mechanical room rough-in and final connection to electrical equipment in progress.
- Interior door frame installation, electrical room buildout, and branch wire pull in sectors 1A and 1B in progress.
- Low voltage cable rough-ins in sector 1A in progress.
- Closing interior walls and drywall finishing in sector 1B in progress.
30-Day Look Ahead:
- Interior wall close-in inspections in sectors 1A and 1B to be completed.
- Hanging of drywall sector 1A to continue.
- Overhead electrical rough-ins on level 2 of the building is ongoing.
- In-wall electrical rough-ins in sector 2B to continue.
- Constructions of underground storm lines MH 24, MH 25, and MH 27 to begin.
- RTU deliveries to site to be completed.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Spray fireproofing and in-wall MEP rough ins on various levels of sector 1A completed.
- One side hanging and in-wall insulation on level 1 of sector 1B completed.
- Installation of welded door frames, exterior windows, and TPO roofing throughout sector 1 completed.
- Installation of interior CMU block walls at sector 2G completed.
- Interior stud wall framing at sector 2K completed.
- Installation of RTU curbs completed.
Work in Progress:
- Interior MEP overhead rough-in on level 2 of sector 1A and 1B in progress.
- Interior stud wall framing in sectors 1A and 2K in progress.
- Hanging of one side drywall on level 1 of sector 1B in progress.
- Soil nail retaining wall at back of school site in progress.
- Installation of stairs 1 and 3 in progress.
- Underground site utilities in west parking lot in progress.
- Installation of exterior windows sector 2 in progress.
30-Day Look Ahead:
- Underground site utilities throughout the project site to continue.
- Hanging of one side drywall in sector 1A to begin.
- Installation of soil nail retaining wall to continue.
- Hanging of second side drywall and drywall finishing for all walls on level 1 of sector 1B to begin.
- MEP rough-in sector 2K mechanical and electrical rooms to begin.
- Installation of knock down and welded door frames in sector 1 to begin.
*Please note: Construction timeframes shown above are subject to change.