PROJECT CONSTRUCTION UPDATES: SEPTEMBER 2022

PROJECT CONSTRUCTION UPDATES: SEPTEMBER 2022

ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Spray fireproofing, installation of exterior metal wall panels, and MEP rough-in at various levels of sector 2K completed.
  • Underground sanitary piping installation at the south connector completed.
  • Curb and gutter installation at the vehicular parking area completed.
  • Drywall close-in on level 1 of sector 1A completed.
  • Building foundation wall waterproofing and backfill at sector 1B completed.

Work In Progress:

  • Site underground storm water piping and grading of parking lot in progress.
  • Spray fireproofing in the connector area in progress.
  • MEPF rough-in in building sectors 1B and 2K, West Commons, and the Gym in progress.
  • Installation of exterior windows and electrical in wall rough-in at sector 1B in progress.
  • Installation of interior door frames on level 1 of sectors 1A and 1B in progress.

30-Day Look Ahead:

  • Interior stud wall framing in sectors 2K and 2G is ongoing.
  • MEP ceiling and wall rough-ins in sectors 1A, 1B, and 2K to continue.
  • Installation of the site underground utilities to continue.
  • Detailing of TPO roof and installation of exterior windows and interior door frames are ongoing.

COLIN L. POWELL K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • All remaining concrete slabs on metal deck completed.
  • Secondary steel girt framing at the 4-story tower completed.
  • Spray fireproofing and overhead MEP rough-in on various levels of the 4-story tower completed.
  • In-wall inspections at the kitchen area completed.
  • Curbs, gutters, and sidewalks at the west parking area completed.

Work in Progress:

  • Secondary steel and spray fireproofing in the 3-story tower in progress.
  • TPO Roofing and overhead MEP rough-ins at the 4-story tower in progress.
  • Installation of exterior metal wall panels in building sector 2 in progress.
  • Interior CMU block wall construction at the aux gym, dance, and choir rooms in progress. 
  • Hanging and finishing of drywall in the kitchen areas in progress.

30-Day Look Ahead:

  • Spray fireproofing, interior stud wall framing, and overhead MEP rough-ins on various levels of the 4-story tower to begin and continue.
  • Asphalt paving at the west parking and access road to begin.
  • Installation of exterior metal wall panels to continue
  • Curb and gutter construction at the east parking area to begin.

DREW-FREEMAN MIDDLE SCHOOL


Project Executive: 
Christian Broyles 
Past Month’s Accomplishments:

  • Drywall top out in sector 1B completed.
  • All exterior brick in sectors 1 and 2 completed.
  • Installation of exterior windows in sectors 1A and 1B completed.
  • In-wall blocking and spray fireproofing on various levels of sector 1A completed.
  • Exterior metal wall panels in sector 2K completed.

Work in Progress:

  • Installation of window framing and exterior windows in building sector 2K in progress.
  • Stud wall framing on level 2 of building sector 1A in progress.
  • Ductwork rough-ins in building sectors 1A and 1B in progress.

30-Day Look Ahead:

  • Installation of stairs 1 and 3 is ongoing.
  • Installation of one-side interior drywall in sector 1B to continue.
  • Installation of exterior windows and MEPF rough-ins in building sector 2K is ongoing.
  • Fire sprinkler rough-ins throughout building sector 1 to continue.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:

  • Exterior metal panel installation at sectors 1B and 2G completed.
  • Underground sanitary tie in at Oliver Street completed.
  • Entrance canopy AVB completed.
  • Exterior window installation and caulking and metal ceiling lath installation at sector 2G completed.
  • In-wall MEP rough-ins on various levels of sector 1A completed.
  • Installation of underground grease interceptor at north site completed.

Work in Progress:

  • Trim out of exterior metal panels and gutters and downspouts in sectors 2G and 2K in progress.
  • Drywall one-siding interior walls, interior door frame installation, and electrical power distribution rough-ins in sector 1A in progress.
  • Fire sprinkler installation, electrical in wall rough-ins, and interior stud wall framing and one-siding drywall in sector 1B in progress.
  • Telecom cabling installation in sectors 1A and 1B in progress.
  • Grading and undercutting of the lower parking lot in progress.
  • Underground site utilities  and gas utilities throughout the site in progress.

30-Day Look Ahead:

  • MEP, sprinkler, and telecom overhead rough-in, testing, and insulation is ongoing.
  • Interior paint at back of house spaces to begin.
  • Curb and gutter construction and base asphalt paving at lower lot to begin.
  • Mechanical and electrical room rough-ins to begin.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Exterior window installation at sector 2K completed.
  • Construction of exterior electrical transformer pad completed.
  • Installation of underground chilled water piping, interior building gas line, and exterior metal panels completed.
  • In-wall MEP rough-ins in sectors 1A and 1B completed.
  • One side drywall in sector 1B completed.
  • All stairs except for main learning stairs completed.
  • Underground sanitary line connection from kitchen to grease interceptor completed.

Work in Progress:

  • Trim, gutters, and downspouts around exterior building perimeter in progress.
  • Overhead ductwork and piping insulation in progress,
  • Electrical room rough-ins in sector 2K in progress.
  • Mechanical room rough-in and final connection to electrical equipment in progress.
  • Interior door frame installation, electrical room buildout, and branch wire pull in sectors 1A and 1B in progress.
  • Low voltage cable rough-ins in sector 1A in progress.
  • Closing interior walls and drywall finishing in sector 1B in progress.

30-Day Look Ahead:

  • Interior wall close-in inspections in sectors 1A and 1B to be completed.
  • Hanging of drywall sector 1A to continue.
  • Overhead electrical rough-ins on level 2 of the building is ongoing. 
  • In-wall electrical rough-ins in sector 2B to continue.
  • Constructions of underground storm lines MH 24, MH 25, and MH 27 to begin.
  • RTU deliveries to site to be completed.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:

  • Spray fireproofing and in-wall MEP rough ins on various levels of sector 1A completed.
  • One side hanging and in-wall insulation on level 1 of sector 1B completed.
  • Installation of welded door frames, exterior windows, and TPO roofing throughout sector 1 completed.
  • Installation of interior CMU block walls at sector 2G completed.
  • Interior stud wall framing at sector 2K completed.
  • Installation of RTU curbs completed.

Work in Progress:

  • Interior MEP overhead rough-in on level 2 of sector 1A and 1B in progress.
  • Interior stud wall framing in sectors 1A and 2K in progress.
  • Hanging of one side drywall on level 1 of sector 1B in progress.
  • Soil nail retaining wall at back of school site in progress.
  • Installation of stairs 1 and 3 in progress.
  • Underground site utilities in west parking lot in progress.
  • Installation of exterior windows sector 2 in progress.

30-Day Look Ahead:

  • Underground site utilities throughout the project site to continue.
  • Hanging of one side drywall in sector 1A to begin.
  • Installation of soil nail retaining wall to continue.
  • Hanging of second side drywall and drywall finishing for all walls on level 1 of sector 1B to begin.
  • MEP rough-in sector 2K mechanical and electrical rooms to begin.
  • Installation of knock down and welded door frames in sector 1 to begin.

*Please note: Construction timeframes shown above are subject to change.